RERA projects in Ghoti Bk. (Ct)
2 projects under 2 MahaRERA registrations, registered 2022–2023. 50% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 1 |
| 2023 | 1 |
Projects in Ghoti Bk. (Ct)
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Murlidhar Park Phase IRajendra Madhukar Kale | P51600050334 | 5 Apr 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Renuka NxYelmame Buildcon | P51600033768 | 8 Mar 2022 | 31 Jan 2027 | 31 May 2027 | Extended 4 mo | 0 |
Other localities in Igatpuri
Most active promoters
By projects registered here, as named on MahaRERA.
- Rajendra Madhukar Kale1 project
- Yelmame Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology