RERA projects in Niphad
67 projects under 67 MahaRERA registrations, registered 2018–2026. 2% have a completion date extended beyond the one promised.
Taluka
67RERA projects
67Registrations
23Completion still due41 past their completion date, 4 marked completed
24 monthsMedian extension beyond promised date2% of registrations extended
0Regulatory casesnone on MahaRERA's lists
30Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 4 |
| 2019 | 4 |
| 2020 | 11 |
| 2021 | 7 |
| 2022 | 10 |
| 2023 | 11 |
| 2024 | 5 |
| 2025 | 5 |
| 2026 | 7 |
Projects in Niphad
67 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Atmarupa ResidencyAnuj Infra | PR1220002602262 | 12 Oct 2026 | 31 Mar 2028 | — | Not yet due | 0 |
| Baswant Trade CenterWayu | PC1220002601719 | 31 Aug 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Jay Malhar ComplexAnuj Infra | PR1220002601608 | 21 Aug 2026 | 31 Mar 2029 | — | Not yet due | 0 |
| Vrundavan Gokuldham DeveloperVrundavan Gokuldham Developer | PR1220002601035 | 6 Jul 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Arihant Business CenterBhandari Infra | PM1220002601005 | 1 Jul 2026 | 10 Jun 2030 | — | Not yet due | 0 |
| Sai Umang HeightsSai Umang Infra | PR1220002600296 | 29 Apr 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Shyam B TownCrestline Buildtech Pvt Ltd | PC1220002600250 | 23 Apr 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Bhandari Greens Phase 2Ujjawala Sohanlal Bhandari | PR1220002501608 | 28 Nov 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Is Residency ParkIs Constructions And Land Developers | P51600080903 | 4 Aug 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Sohan SignatureSohanlal Bhandari Realty | PR1220002500388 | 28 Jul 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Manas Vishram ComplexMaa Krupa Buildcon | P51600079341 | 28 Feb 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Narayan HightsMauli Construction And Developers | P51600078936 | 21 Jan 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Aero CityAero City Realtors | P51600077326 | 6 Aug 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Sahil NagarSohanlal Bhandari Realty | P51600076644 | 18 Jun 2024 | 31 Dec 2025 | — | Promised date passed | 0 |
| Universal PrideUniversal Buildcon | P51600055655 | 5 Apr 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| SaisquareVijay Vasudev Lalwani | P51600055527 | 2 Apr 2024 | 1 Jan 2026 | — | Promised date passed | 0 |
| Sohan ParkSiddharth Sohanlal Bhandari | P51600054825 | 15 Feb 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Mahalaxmi HeightsPrashant Genu Pagar | P51600053630 | 21 Nov 2023 | 31 Jul 2026 | — | Promised date passed | 0 |
| Sohan City Phase 1 LasalgaonSiddharth Sohanlal Bhandari | P51600053469 | 6 Nov 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Nirmal ParkNirmal Samruddhi | P51600053417 | 31 Oct 2023 | 25 Feb 2026 | — | Promised date passed | 0 |
| Sohan City Phase 2 LasalgaonSagar Sohanlal Bhandari | P51600053297 | 23 Oct 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Shreeram ResidencyParmanand Shrikrishna Patil | P51600051163 | 1 Jun 2023 | 31 May 2025 | — | Promised date passed | 0 |
| Atmakrupa Row HousesSagar Gorakh Bagul | P51600050552 | 21 Apr 2023 | 31 Jan 2025 | — | Promised date passed | 0 |
| Kalpataru Baug - Phase 2Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil Bhambere | P51600050445 | 12 Apr 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Bhumi HeightsBhumi Developers | P51600050009 | 6 Mar 2023 | 30 Sep 2025 | — | Promised date passed | 0 |
Other talukas in Nashik
Most active promoters
By projects registered here, as named on MahaRERA.
- Siddharth Sohanlal Bhandari3 projects
- Ujjawala Sohanlal Bhandari3 projects
- Anuj Infra2 projects
- Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil Bhambere2 projects
- Parmanand Shrikrishna Patil2 projects
- Sagar Sohanlal Bhandari2 projects
- Sandeep Kantilal Kochar2 projects
- Sohanlal Bhandari Realty2 projects
- Abhishek Balasaheb Deshmukh1 project
- Abhishek Builders And Developers1 project
Data through12 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology