8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects68
Registrations68
Completion still due2441 past their date
Median extension4 months26% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

68 MahaRERA registrations in Niphad and the places within it

4 completed8 not yet due16 extended, not yet due37 past even the latest date3 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Niphad

68 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Bhumi HeightsBhumi DevelopersCompleted—67%
Swapnapurti AppartmentAvhad Builders And Developers LimitedCompleted——
Vrundavan City Pride MallVrundavan Builders1 yr 7 mo late—18%
Martand HeightsTara DevelopersCompleted—30%
Bhandari Greens Phase 3Ujjawala Sohanlal BhandariCompleted—62%
Lotus ParkAbhishek Balasaheb DeshmukhCompleted—100%
Nirmal Heights 05Gangaprassad Shivprasad SharmaCompleted——
Shree Ganesh ApartmentSachin Ashok Dhatrak2 yrs 10 mo late——
Yamuna PrideYamuna ConstructionsDue Apr 2028, extended 4 mo—20%
Rudransh ParkAshok Shivnarayan LaddhaCompleted—15%
Balaji HeightsAditya Dilip Bhandari3 yrs 7 mo late——
Siddhivinayak HeightsSiddhivinayak BuildtechCompleted——
Vinayak NiwasParmanand Shrikrishna PatilCompleted—38%
Sohan City Phase 1Siddharth Sohanlal BhandariCompleted—96%
Sohan City Phase 2Sagar Sohanlal Bhandari10 mo late——
Baphana EmpireBaphana Infra2 yrs 4 mo late—46%
Sai TaraGurukripa Builders and DevelopersCompleted—40%
Nirmal VishwaNirmal Construction2 yrs 11 mo late——
Shri Anand DarshanManisha Sandip KocharCompleted—68%
Bhandari GreensUjjawala Sohanlal BhandariCompleted—91%
Kalpataru Baug - Phase 1Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil BhambereDue Dec 2026—92%
Vinchur PlazaVighanharta Developers And BuildersCompleted—18%
Siddhi ParkSiddhi DevelopersCompleted——
Vrindavan HeightsDwarka Ashirwad And Associates2 yrs 6 mo late——
Radha TowerSamarth Group4 yrs 10 mo late—75%
Niphad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Siddharth Sohanlal Bhandari3 projects
  2. Ujjawala Sohanlal Bhandari3 projects
  3. Anuj Infra2 projects
  4. Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil Bhambere2 projects
  5. Neeta Sagar Bagul2 projects
  6. Sagar Sohanlal Bhandari2 projects
  7. Sandeep Kantilal Kochar2 projects
  8. Sohanlal Bhandari Realty2 projects
  9. Abhishek Balasaheb Deshmukh1 project
  10. Abhishek Builders And Developers1 project

Niphad, in questions

How many projects in Niphad run late?

8 in 10 MahaRERA registrations (53 of 68): their completion date was extended or has passed, data through 27 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Niphad by Deedo. Medians on fewer than 3 deeds are not shown.

Data through27 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology