Radha Tower
Certificate SignedOzar (Ct), Nashik 422206 |Promoter: Samarth Group
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, Shop16 units in all
- Address
- S. No. 1114 To 1118, Main Road, Ozar MigPIN 422206
- Designated bank account
- 82
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2021
The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 2 Sep 2020
- Promised
- 30 Dec 2021
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600026264 | 2 Sep 2020 | 30 Dec 2021 | 30 Dec 2021 | Samarth Group | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Main building | 5 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
12 of 16 units booked (75%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.87 sq m · 461 sq ft | 3 | 1 |
| 1BHK | 44.6 sq m · 480 sq ft | 3 | 3 |
| 2BHK | 53.41 sq m · 575 sq ft | 3 | 2 |
| 2BHK | 54.41 sq m · 586 sq ft | 3 | 2 |
| Shop | 11.22 sq m · 121 sq ft | 1 | 1 |
| Shop | 11.56 sq m · 124 sq ft | 3 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 19 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 17 Aug 2020Source
Legal
Show all 20 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 17 Aug 2020Source
- 1 Details of encumbrancesAffidavit Encumbrances.pdf · uploaded 18 Aug 2020Source
- 1 Declaration in FORM BForm B_Developer.pdf · uploaded 18 Aug 2020Source
- 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 19 Aug 2020Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 27 Aug 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE_FORM 31.pdf · uploaded 27 Aug 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Samarth.pdf · uploaded 4 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)samarth rera audit1.pdf · uploaded 4 Jan 2022Source
- 1 OtherApplication for CC.pdf · uploaded 4 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 Radha Tower.pdf · uploaded 16 Dec 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ozar (CT), Niphad taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 1113
- South
- S No 1154
- East
- Road
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sachin Vinayak Baviskar | — |
| Chartered accountant | Vijay Jibhau Nikam | — |
| Engineer | Sachin Vinayak Baviskar | — |
Source: MahaRERA project page. Contact details are not shown.