5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects29
Registrations29
Completion still due1514 past their date
Median extension4 months48% of registrations extended
Regulatory cases1on 1 project
Sinnar(M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

29 MahaRERA registrations in Sinnar(M Cl)

3 not yet due12 extended, not yet due14 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Sinnar(M Cl)

29 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shri Ganesh HeightsShree Ganesh ConstructionDue Apr 2034, extended 4 mo——
Pragati Garden Phase IINew Pragati Construction CompanyDue Apr 2029, extended 4 mo——
Samarth VrindavanAvadhoot ConstructionDue Oct 2027, extended 4 mo——
Aastha HorizonDeacon Infrastructures Private LimitedDue Apr 2028, extended 4 mo—0%
Ramtek AyodhyaShinde ConstructionDue Apr 2033, extended 4 mo—0%
Shree Ganesh EmpireShree Ganesh ConstructionDue Apr 2033, extended 4 mo—0%
Nirmiti GloryNirmiti Builders And DevelopersDue Apr 2028, extended 4 mo—0%
Vedant AanandvanGorakshnath Dashrath MhaskeDue Apr 2030, extended 4 mo—0%
Daulat ApartmentSunita Sanjay PatilDue Jul 2028, extended 4 mo—0%
Yashwant Row BungalowPankaj Ashok More1 yr 10 mo late—333%
Vedant Prasad ApartmentGorakshanath Dashrath MhaskeDue Dec 2028—48%
Samarth HeightsAtul Vilas KankateDue Nov 2027——
Swapna HeightsSwapnpurti BuildersDue Apr 2027, extended 4 mo——
Vastupurti GalaxyVaibhav Dattatrya Mutrak3 yrs late—0%
Rajeshree EmpireHitendra Madhukar MahatmeDue Jan 2028——
Vedant Aarti ApartmentVandana Gorakshnath Mhaske10 mo late—0%
Shree Ganesh NakshtraSiddhivinayak DevelopersDue Dec 2027, extended 3 yrs—80%
Golden HeightsBalkrushna Keshraj Mehekarkar2 yrs 2 mo late—0%
Shubharambh ResidencyLaxmi Buildcon2 yrs 2 mo late—100%
Pushpanjali ResidencyArjun Karbhari Kedar3 yrs 7 mo late—13%
Prathmesh ParadiseRavikant Vishwanath Ghuge4 yrs 7 mo late—100%
Rachna HousesDnyaneshwar Kacharu Ilag2 yrs 4 mo late—82%
Vedant Pooja ApartmentPravin Balasaheb Kedar3 yrs 2 mo late—100%
Vedant Bhakti ApartmentVaijayanta V Nagare and Kamal E Shelke partner of BHAKTI CONSTRUCTION3 yrs 1 mo late—100%
Sai SharddhaRahul Balasaheb Targe2 yrs 4 mo late—73%

Most active promoters

  1. Shree Ganesh Construction2 projects
  2. Arjun Karbhari Kedar1 project
  3. Atul Vilas Kankate1 project
  4. Avadhoot Construction1 project
  5. Balkrushna Keshraj Mehekarkar1 project
  6. Deacon Infrastructures Private Limited1 project
  7. Deepak Kalyanji Chande1 project
  8. Dnyaneshwar Kacharu Ilag1 project
  9. Gorakshanath Dashrath Mhaske1 project
  10. Gorakshnath Dashrath Mhaske1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology