Sinnar(M Cl), Nashik
Deedo IDDL-NSK-SINNAR-25 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects29
Registrations29
Completion still due1514 past their date
Median extension4 months48% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
29 MahaRERA registrations in Sinnar(M Cl)
3 not yet due12 extended, not yet due14 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Sinnar(M Cl)
29 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shri Ganesh HeightsShree Ganesh Construction | Due Apr 2034, extended 4 mo | — | — |
| Pragati Garden Phase IINew Pragati Construction Company | Due Apr 2029, extended 4 mo | — | — |
| Samarth VrindavanAvadhoot Construction | Due Oct 2027, extended 4 mo | — | — |
| Aastha HorizonDeacon Infrastructures Private Limited | Due Apr 2028, extended 4 mo | — | 0% |
| Ramtek AyodhyaShinde Construction | Due Apr 2033, extended 4 mo | — | 0% |
| Shree Ganesh EmpireShree Ganesh Construction | Due Apr 2033, extended 4 mo | — | 0% |
| Nirmiti GloryNirmiti Builders And Developers | Due Apr 2028, extended 4 mo | — | 0% |
| Vedant AanandvanGorakshnath Dashrath Mhaske | Due Apr 2030, extended 4 mo | — | 0% |
| Daulat ApartmentSunita Sanjay Patil | Due Jul 2028, extended 4 mo | — | 0% |
| Yashwant Row BungalowPankaj Ashok More | 1 yr 10 mo late | — | 333% |
| Vedant Prasad ApartmentGorakshanath Dashrath Mhaske | Due Dec 2028 | — | 48% |
| Samarth HeightsAtul Vilas Kankate | Due Nov 2027 | — | — |
| Swapna HeightsSwapnpurti Builders | Due Apr 2027, extended 4 mo | — | — |
| Vastupurti GalaxyVaibhav Dattatrya Mutrak | 3 yrs late | — | 0% |
| Rajeshree EmpireHitendra Madhukar Mahatme | Due Jan 2028 | — | — |
| Vedant Aarti ApartmentVandana Gorakshnath Mhaske | 10 mo late | — | 0% |
| Shree Ganesh NakshtraSiddhivinayak Developers | Due Dec 2027, extended 3 yrs | — | 80% |
| Golden HeightsBalkrushna Keshraj Mehekarkar | 2 yrs 2 mo late | — | 0% |
| Shubharambh ResidencyLaxmi Buildcon | 2 yrs 2 mo late | — | 100% |
| Pushpanjali ResidencyArjun Karbhari Kedar | 3 yrs 7 mo late | — | 13% |
| Prathmesh ParadiseRavikant Vishwanath Ghuge | 4 yrs 7 mo late | — | 100% |
| Rachna HousesDnyaneshwar Kacharu Ilag | 2 yrs 4 mo late | — | 82% |
| Vedant Pooja ApartmentPravin Balasaheb Kedar | 3 yrs 2 mo late | — | 100% |
| Vedant Bhakti ApartmentVaijayanta V Nagare and Kamal E Shelke partner of BHAKTI CONSTRUCTION | 3 yrs 1 mo late | — | 100% |
| Sai SharddhaRahul Balasaheb Targe | 2 yrs 4 mo late | — | 73% |
Nearby: other localities in Sinnar
Most active promoters
- Shree Ganesh Construction2 projects
- Arjun Karbhari Kedar1 project
- Atul Vilas Kankate1 project
- Avadhoot Construction1 project
- Balkrushna Keshraj Mehekarkar1 project
- Deacon Infrastructures Private Limited1 project
- Deepak Kalyanji Chande1 project
- Dnyaneshwar Kacharu Ilag1 project
- Gorakshanath Dashrath Mhaske1 project
- Gorakshnath Dashrath Mhaske1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology