RERA projects in Shinde
9 projects under 9 MahaRERA registrations, registered 2017–2025. 11% have a completion date extended beyond the one promised.
Locality
9RERA projects
9Registrations
4Completion still due5 past their completion date, 1 marked completed
92 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 2 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 1 |
| 2025 | 1 |
Projects in Shinde
9 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mauli PrideDeepak Baban Chaudhari | P51600080647 | 23 Jun 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| The Nexon CityRajendra Madhav Shelar | P51600077870 | 7 Nov 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Shivalay ApartmentBharat Suresh Dheringe | P51600048374 | 27 Dec 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Siddhi Samruddhi Park Phase VRenuka Mata Builders And Developers | P51600032525 | 10 Jan 2022 | 31 Oct 2024 | — | Promised date passed | 0 |
| Siddhi Samruddhi Park Phase - 4Renuka Mata Builders And Developers | P51600026896 | 3 Nov 2020 | 30 Apr 2024 | — | Promised date passed | 0 |
| Sai Swami ApartmentsPratibha Nilesh More | P51600021951 | 25 Aug 2019 | 22 Jul 2022 | — | Completed | 0 |
| Mauli ParkMauli Builders And Developers | P51600017400 | 9 Aug 2018 | 20 Jul 2022 | — | Promised date passed | 0 |
| Renuka Estate Phase 1Rajee Infrastructure | P51600016228 | 25 Apr 2018 | 1 May 2021 | 31 Dec 2028 | Extended 91 mo | 0 |
| Shree Gajanan Industrial LayoutGirish Sudhakar Thakur | P51600010412 | 24 Aug 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
Other localities in Nashik
Most active promoters
By projects registered here, as named on MahaRERA.
- Renuka Mata Builders And Developers2 projects
- Bharat Suresh Dheringe1 project
- Deepak Baban Chaudhari1 project
- Girish Sudhakar Thakur1 project
- Mauli Builders And Developers1 project
- Pratibha Nilesh More1 project
- Rajee Infrastructure1 project
- Rajendra Madhav Shelar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology