9 projects under 9 MahaRERA registrations, registered 2017–2025. 11% have a completion date extended beyond the one promised.

Locality
9RERA projects
9Registrations
4Completion still due5 past their completion date, 1 marked completed
92 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20182
20191
20201
20210
20222
20230
20241
20251

Projects in Shinde

9 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mauli PrideDeepak Baban ChaudhariP5160008064723 Jun 202531 Mar 2028—Not yet due0
The Nexon CityRajendra Madhav ShelarP516000778707 Nov 202431 Dec 2029—Not yet due0
Shivalay ApartmentBharat Suresh DheringeP5160004837427 Dec 202231 Dec 2026—Not yet due0
Siddhi Samruddhi Park Phase VRenuka Mata Builders And DevelopersP5160003252510 Jan 202231 Oct 2024—Promised date passed0
Siddhi Samruddhi Park Phase - 4Renuka Mata Builders And DevelopersP516000268963 Nov 202030 Apr 2024—Promised date passed0
Sai Swami ApartmentsPratibha Nilesh MoreP5160002195125 Aug 201922 Jul 2022—Completed0
Mauli ParkMauli Builders And DevelopersP516000174009 Aug 201820 Jul 2022—Promised date passed0
Renuka Estate Phase 1Rajee InfrastructureP5160001622825 Apr 20181 May 202131 Dec 2028Extended 91 mo0
Shree Gajanan Industrial LayoutGirish Sudhakar ThakurP5160001041224 Aug 201730 Jun 2019—Promised date passed0

Other localities in Nashik

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Renuka Mata Builders And Developers2 projects
  2. Bharat Suresh Dheringe1 project
  3. Deepak Baban Chaudhari1 project
  4. Girish Sudhakar Thakur1 project
  5. Mauli Builders And Developers1 project
  6. Pratibha Nilesh More1 project
  7. Rajee Infrastructure1 project
  8. Rajendra Madhav Shelar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology