Skip to content
Deedo home
Menu

RERA projects in Palse

8 projects under 8 MahaRERA registrations, registered 2017–2025. None has an extended completion date on record.

Locality
8RERA projects
8Registrations
2Completion still due6 past their completion date, 2 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181
20192
20201
20211
20220
20231
20240
20251

Projects in Palse

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vighnaharta ApartmentAshtavinayak ConstructionP5160007973824 Mar 202527 Dec 2027—Not yet due0
Mayureshwar Park And Row HousesAshtvinayak ConstructionP5160004975324 Feb 202331 Aug 2025—Promised date passed0
MatruchayaBaldeosingh Jaisingh BaggaP516000320663 Dec 202115 Aug 2030—Not yet due0
Laxmi ParkRishi Builders And DevelopersP5160002525527 Mar 202025 Dec 2022—Promised date passed0
Sheetal Residency Building No 2 and 3Shri Sadguru Shivram Construction Pvt LtdP5160002027031 Mar 201915 Apr 2025—Completed0
Siddhivinayak ParkAshtvinayak ConstructionP516000197585 Mar 201928 Feb 2023—Promised date passed0
Shiv Malhar AppartmentBharat Suresh DheringeP5160001538821 Feb 201830 Jan 2021—Promised date passed0
Sheetal Residency Building No 1Shri Sadaguru Shivram Constructions Pvt LtdP516000027724 Aug 201715 Oct 2024—Completed0

Other localities in Nashik

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ashtvinayak Construction2 projects
  2. Ashtavinayak Construction1 project
  3. Baldeosingh Jaisingh Bagga1 project
  4. Bharat Suresh Dheringe1 project
  5. Rishi Builders And Developers1 project
  6. Shri Sadaguru Shivram Constructions Pvt Ltd1 project
  7. Shri Sadguru Shivram Construction Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology