Jalalpur, Nashik
Deedo IDDL-NSK-JALALPUR3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects8
Registrations8
Completion still due08 past their date
Median extension8 months25% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
8 MahaRERA registrations in Jalalpur
8 past even the latest date
Extended registrations moved their completion date by a median of 8 months.
Projects in Jalalpur
8 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Mangalam ApartmentAarya Imex | 7 mo late | — | 0% |
| Aaradhya NakshatraShreyash Buildcon | 10 mo late | — | 15% |
| Omkar EmeraldOmkar Builders And Developers | 1 yr late | — | 11% |
| Morya DarshanOmkar Builders And Developers | 1 yr 6 mo late | — | 0% |
| Siddhivinayak HeightsShantanu Pratapsinh Patil | 1 yr 10 mo late | — | 74% |
| Morya GalaxyOmkar Buildcon | 2 yrs 4 mo late | — | 0% |
| Morya Pride ApartmentOmkar Buildcon | 2 yrs 1 mo late | — | 0% |
| The WaterfrontHarish Veerappa Kanchan | 8 yrs 1 mo late | — | 38% |
Nearby: other localities in Nashik
Most active promoters
- Omkar Buildcon2 projects
- Omkar Builders And Developers2 projects
- Aarya Imex1 project
- Harish Veerappa Kanchan1 project
- Shantanu Pratapsinh Patil1 project
- Shreyash Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology