RERA projects in Govardhan

5 projects under 6 MahaRERA registrations, registered 2022–2026. None has an extended completion date on record.

Locality
5RERA projects
6Registrationssome projects hold several
5Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
1Regulatory caseson 1 project
91Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20232
20240
20251
20262

Projects in Govardhan

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Wind ChimesPR EnterprisesPR122101260168327 Aug 202631 Dec 2032—Not yet due0
Golden Peacock-Phase OneDeepak Infra And Homes Private LimitedPR12200025026266 Mar 202631 Dec 2032—Not yet due0
RiverdaleArpanna Motors Private LimitedP51600053803, PR12210125017241 Dec 202331 Dec 2027—Not yet due0
Abh Nature TalesAbh Developers Private LimitedP5160005326823 Oct 202328 Apr 2027—Not yet due0
SERENITY at Ashok AstoriaPeninsula Land LimitedP516000336612 Mar 202231 Mar 2026—Promised date passed1

Other localities in Nashik

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Abh Developers Private Limited1 project
  2. Arpanna Motors Private Limited1 project
  3. Deepak Infra And Homes Private Limited1 project
  4. Peninsula Land Limited1 project
  5. PR Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology