Niphad, Nashik
Deedo IDDL-NSK-NIPHAD-210 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects5
Registrations5
Completion still due14 past their date
Median extension4 months20% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
5 MahaRERA registrations in Niphad
1 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Niphad
5 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Is Residency ParkIs Constructions And Land Developers | Due Jul 2027, extended 4 mo | — | — |
| Sahil NagarSohanlal Bhandari Realty | 11 mo late | — | 73% |
| Vrindavan HeightsDwarka Ashirwad And Associates | 2 yrs 7 mo late | — | — |
| Bagmar PlazaBagmar Pradeep Kantilal HUF | 3 yrs 5 mo late | — | 13% |
| Renuka FloraRenuka Builders Architect And Developers | Completed | — | — |
Nearby: other villages in Niphad
Most active promoters
- Bagmar Pradeep Kantilal Huf1 project
- Dwarka Ashirwad And Associates1 project
- Is Constructions And Land Developers1 project
- Renuka Builders Architect And Developers1 project
- Sohanlal Bhandari Realty1 project
Niphad, in questions
How many projects in Niphad run late?
10 in 10 MahaRERA registrations (5 of 5): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Niphad by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology