Sudarshan Empire
Deedo IDDP-NSK-1J14Completion was pushed back 4 months, to Mar 2030; no MahaRERA orders on record; 0% of its units are booked.
Dasak, Nashik 422101 · by Sudarshan Keru Sangale
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2030
- This projectRegistered 3 Feb 2025, completion promised 7 Nov 2029, revised to 7 Mar 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600079093
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600079093 | 3 Feb 2025 | 7 Nov 2029 | 7 Mar 2030 | Sudarshan Keru Sangale | Project page |
Documents59
1 document held by Deedo, 58 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card-sangale.pdf · uploaded 8 Nov 2024Source
Legal
- Legal Title reportTitle Report - Sudarshan Empire.pdf · uploaded 8 Nov 2024Source
- Declaration Form BFORM B Affidavit-DEVELOPERS-1.pdf · uploaded 11 Nov 2024Source
- Other – Legalself declaration.pdf · uploaded 11 Dec 2024Source
- Other – LegalDevelopment Agreement_11zon (4).pdf · uploaded 11 Dec 2024Source
Show all 59 documentsShow fewer documents
Migrated
- 1 a Details of encumbrances concerned to FinanceSELF DECLERATION BANK AND LEGLE EMBC.pdf · uploaded 11 Nov 2024Source
- 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 11 Nov 2024Source
- 1 Declaration in FORM BFORM B Affidavit-DEVELOPERS-1.pdf · uploaded 11 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2-new fF.pdf · uploaded 11 Nov 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE1.pdf · uploaded 11 Nov 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentCOMMENCEMENT PLAN1_compressed.pdf · uploaded 11 Nov 2024Source
- 1 Declaration about Commencement Certificatedeclaration about commencement.pdf · uploaded 11 Nov 2024Source
- 1 b Details of encumbrances concerned to LegalSELF DECLERATION BANK AND LEGLE EMBC.pdf · uploaded 11 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3-new.pdf · uploaded 12 Nov 2024Source
- 1 CERSAI detailsABOUT CERSAI REPORT.pdf · uploaded 12 Nov 2024Source
- 1 Deviation Report with respect to Allotment letterdeviation report-Allotment.pdf · uploaded 12 Nov 2024Source
- 1 Deviation Report with respect to model copy of Agreementdeviation report-agreement.pdf · uploaded 12 Nov 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest -saNGALE.pdf · uploaded 12 Nov 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format-B.pdf · uploaded 12 Nov 2024Source
- 2 Other – TechnicalNMC Mail-REA51600165592.pdf · uploaded 13 Nov 2024Source
- 3 Other – TechnicalFROM-32 DECLARATION ABOUT-CC-Final.pdf · uploaded 13 Nov 2024Source
- 4 Other – TechnicalLetter of Project completion higer site.pdf · uploaded 13 Nov 2024Source
- 2 a Details of encumbrances concerned to Financeencumbrace certificate.pdf · uploaded 29 Nov 2024Source
- 1 Proforma of Allotment letterModel Allotment letter-NEW.pdf · uploaded 29 Nov 2024Source
- 2 b Details of encumbrances concerned to Legalencumbrace certificate.pdf · uploaded 29 Nov 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for secured and unsecured finance.pdf · uploaded 29 Nov 2024Source
- 1 Other – LegalDevelopment Agreement_11zon (4).pdf · uploaded 11 Dec 2024Source
- 2 Other – Legalself declaration.pdf · uploaded 11 Dec 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format- A Openingof RERA Designated bank account-final.pdf · uploaded 13 Jan 2025Source
- 1 Proforma of Agreement for saleAgreement For Sale.pdf · uploaded 13 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 final.pdf · uploaded 20 Jan 2025Source
- 1 Other – Technicaldeclaration-cum-undertaking.pdf · uploaded 21 Jan 2025Source
- Withdrawal Update Form 1form-1.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 2form-2.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 3Form-3-new.pdf · uploaded 24 Feb 2026Source
- Withdrawal Update Form 1fomr-1-f.pdf · uploaded 5 Mar 2026Source
- Withdrawal Update Form 1form-1-f.pdf · uploaded 5 Mar 2026Source
- Withdrawal Update Form 2fomr-2-f.pdf · uploaded 5 Mar 2026Source
- Withdrawal Update Form 2form-2.pdf · uploaded 5 Mar 2026Source
- Withdrawal Update Form 3Form-3-new.pdf · uploaded 5 Mar 2026Source
- Withdrawal Update Form 3Form-3-new.pdf · uploaded 5 Mar 2026Source
- Form 5 (FY 2024-2025)FORM-5.pdf · uploaded 26 Mar 2026Source
- Withdrawal Update Form 1FORM-1-f.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 2FORM-2-f.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 3Form-3-new.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1form-1.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 2form-2.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 3Form-3-new.pdf · uploaded 10 Oct 2026Source
Technical
- DocumentCOMMENCEMENT PLAN1_compressed.pdf · uploaded 11 Nov 2024Source
- Documentlayout plan.pdf · uploaded 11 Nov 2024Source
- Other – TechnicalLetter of Project completion higer site.pdf · uploaded 13 Nov 2024Source
- Other – TechnicalFROM-32 DECLARATION ABOUT-CC-Final.pdf · uploaded 13 Nov 2024Source
- Other – TechnicalNMC Mail-REA51600165592.pdf · uploaded 13 Nov 2024Source
- Other – Technicaldeclaration-cum-undertaking.pdf · uploaded 21 Jan 2025Source
Technical (Architect)
- Documentform-1.pdf · uploaded 10 Oct 2026Source
Technical (Engineer)
- Documentform-2.pdf · uploaded 10 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No. 00 Sr. NO. 10/1/1 Mouje Nandur Dasak
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Hospital Developers, Hospital Land Owner, Shop, Shop Land owner, Shop Landowner, Shop owner, Shop Owner57 units in all
- Address
- Plot No. 00 Sr. NO. 10/1/1 Mouje Nandur Dasak, Nandur Dasak, DasakPIN 422101
- Village
- Nashik (M Corp.), Nashik taluka
- Location
- 19.97795, 73.83317
- Land area for this project
- 3,038 sq m (32,696 sq ft)
- Permissible built-up area
- 9,218 sq m (99,227 sq ft)
- Sanctioned built-up area
- 3,790 sq m (40,796 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No. 00 Sr. NO. 10/1/1 Mouje Nandur Dasak
Boundaries
- North
- CTS No 469 P
- South
- CTS No 502
- East
- 30 Mtr Road
- West
- CTS No 468
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking57 units
0 of 57 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Hospital Developers | 426.19 sq m · 4,587 sq ft | 2 | 0 |
| Hospital Land Owner | 426.15 sq m · 4,587 sq ft | 1 | 0 |
| Shop | 8.69 sq m · 94 sq ft | 1 | 0 |
| Shop | 9.43 sq m · 102 sq ft | 1 | 0 |
| Shop | 9.47 sq m · 102 sq ft | 1 | 0 |
| Shop | 9.48 sq m · 102 sq ft | 4 | 0 |
| Shop | 9.61 sq m · 103 sq ft | 2 | 0 |
| Shop | 14.24 sq m · 153 sq ft | 1 | 0 |
Show all 45 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 14.66 sq m · 158 sq ft | 1 | 0 |
| Shop | 16.91 sq m · 182 sq ft | 2 | 0 |
| Shop | 16.94 sq m · 182 sq ft | 1 | 0 |
| Shop | 17.25 sq m · 186 sq ft | 1 | 0 |
| Shop | 17.54 sq m · 189 sq ft | 1 | 0 |
| Shop | 18.18 sq m · 196 sq ft | 1 | 0 |
| Shop | 18.51 sq m · 199 sq ft | 1 | 0 |
| Shop | 18.72 sq m · 202 sq ft | 1 | 0 |
| Shop | 18.81 sq m · 202 sq ft | 1 | 0 |
| Shop | 19.06 sq m · 205 sq ft | 1 | 0 |
| Shop | 21.52 sq m · 232 sq ft | 1 | 0 |
| Shop | 42.32 sq m · 456 sq ft | 1 | 0 |
| Shop | 45.15 sq m · 486 sq ft | 1 | 0 |
| Shop | 51.64 sq m · 556 sq ft | 1 | 0 |
| Shop | 59.75 sq m · 643 sq ft | 1 | 0 |
| Shop | 61.76 sq m · 665 sq ft | 1 | 0 |
| Shop | 65.02 sq m · 700 sq ft | 1 | 0 |
| Shop | 70.98 sq m · 764 sq ft | 1 | 0 |
| Shop | 74.08 sq m · 797 sq ft | 1 | 0 |
| Shop | 131.52 sq m · 1,416 sq ft | 1 | 0 |
| Shop Land owner | 49.33 sq m · 531 sq ft | 1 | 0 |
| Shop Landowner | 8.69 sq m · 94 sq ft | 1 | 0 |
| Shop Landowner | 9.43 sq m · 102 sq ft | 1 | 0 |
| Shop Landowner | 9.47 sq m · 102 sq ft | 3 | 0 |
| Shop Landowner | 14.24 sq m · 153 sq ft | 2 | 0 |
| Shop Landowner | 16.63 sq m · 179 sq ft | 1 | 0 |
| Shop Landowner | 16.91 sq m · 182 sq ft | 2 | 0 |
| Shop Landowner | 16.94 sq m · 182 sq ft | 1 | 0 |
| Shop Landowner | 18.81 sq m · 202 sq ft | 1 | 0 |
| Shop Landowner | 43.75 sq m · 471 sq ft | 1 | 0 |
| Shop Landowner | 53.56 sq m · 577 sq ft | 1 | 0 |
| Shop Landowner | 56.79 sq m · 611 sq ft | 2 | 0 |
| Shop Landowner | 61.79 sq m · 665 sq ft | 1 | 0 |
| Shop Landowner | 61.81 sq m · 665 sq ft | 1 | 0 |
| Shop Landowner | 272.34 sq m · 2,931 sq ft | 1 | 0 |
| Shop owner | 18.79 sq m · 202 sq ft | 2 | 0 |
| Shop Owner | 70.9 sq m · 763 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mohit Karnavat Karnavat | — |
| Chartered accountant | Anil Khetamal Dahiya | — |
| Chartered accountant | Piyush Lalit Verma Lalit Verma | — |
| Engineer | Jayesh Makwana Makwana | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dasak
- Vishwaraj Co-op. housing society LtdRERA PR1220002602346
- Silk RouteRERA PM1220002601778
- Shilp SrushtiRERA PR1220002601333
- Guru Sneh ApartmentsRERA PM1220002601022
- Mahesh ResidencyRERA P51600080884
- Aishwarya HeightsRERA P51600079109
- Shri Laxmi Narayan VillasRERA P51600051490
- Mahaveer HeightsRERA P51600034067
All 10 projects in Dasak · Compare Sudarshan Empire with another project