7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Saptrang Co-operative Housing Society LimitedSaptrang Co op Housing Society LimitedDue Feb 2028, extended 4 mo——
AashiyanaSkyline Aashiyana LLPDue Oct 2028, extended 4 mo——
Muktaprabha AppartmentJ And B BuildersDue Apr 2027, extended 4 mo——
Shree Maruti Mangal ApartmentS K ConstructionDue Apr 2027, extended 4 mo——
Hill Top Co Operative Housing Society Limited NashikViraj Housing & Land DevelopersDue Apr 2027, extended 4 mo——
Rivernest ApartmentAdikara DevelopersDue Nov 2028, extended 4 mo——
Saptashrungi AradhanaTrimurti BuildtechCompleted——
Aaradhya Marigold ManorShreyash BuildconDue Apr 2027, extended 4 mo——
Arjun HeightsSky DevelopersDue Dec 2027, extended 4 mo——
Hill Top Heights ApartmentDhruvika DevelopersDue Jul 2027, extended 4 mo——
Jagdamb ApartmentJ B ConstructionDue Oct 2028, extended 4 mo——
Om Sai HaightKanhaiya RealtyDue Oct 2029, extended 4 mo——
Guru Tirth ApartmentAnup Builders & DevelopersCompleted——
Palde PlazaH R Builders And Developers LLPDue Apr 2028, extended 4 mo——
Raghuveer ParkRNK Landmarks LLPDue Apr 2028, extended 4 mo——
Ashtapad Phase VI Building B C DArkk Builders And DevelopersDue Apr 2030, extended 4 mo——
Pratipada Co-Op Housing SocietySatish Balkrishna ParanjapeDue Apr 2029, extended 4 mo——
Royal CliffVaastu WorldDue Apr 2029, extended 4 mo——
Viraj PlatinumShah Property Creation LLPDue Apr 2027, extended 4 mo——
Serene MeadowsBhushan Laxmanrao ThanganDue Apr 2028, extended 4 mo——
Vrindavan HeightsRavindra Rangrao MistryDue Apr 2029, extended 4 mo——
Yashogandh Co-Op Housing Society LtdAssociated Civil Engineers and SurveyorsDue Nov 2027, extended 4 mo——
Hill View Apartment Co Op Housing Society LtdAr InfraDue Jul 2027, extended 4 mo——
Murli VrundavanPcg Technocrete11 mo late——
Padmanabhan HeightsSushant Jibhau GangurdeDue Apr 2027, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology