7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shree Shrimant LegacyRohan EnterprisesDue Apr 2028, extended 4 mo——
Snehal Pride ApartmentSunny InfrastructureDue Apr 2028, extended 4 mo——
Sohamani Co-operative Housing Society Ltd. NashikAmol Shashikant AhirraoDue Apr 2028, extended 4 mo——
Samartha MalharChandrakant Ramkrishna GodseDue Apr 2031, extended 4 mo——
Shiv EmpireVipulkumar Mansukhbhai ChauhanDue Apr 2027, extended 4 mo——
Tirupati TowerTirupati BuilderDue Jul 2027, extended 4 mo——
Siddhivinayak Tower ApartmentSandhya PatilDue Jan 2029, extended 4 mo——
Elica DelightElica ConstructionDue Dec 2032——
Valji ResidenceShiva InfraDue Nov 2027, extended 4 mo——
Yamuna ParkYamuna Greens BuildconDue Apr 2029, extended 4 mo——
Atharva Sky ParkSiddhivinayak BuildtechDue Apr 2030, extended 4 mo——
Sky View PanchavatiGreen InfraDue Aug 2027, extended 4 mo——
Ekdanta HeightsSukhakarta BuildersDue Apr 2029, extended 4 mo——
Icchamani EnclaveIcchamani BuildconCompleted——
Laxmiprabha And LaxmichayaSoham ConstructionsDue Apr 2029, extended 4 mo——
Manas Vishram ComplexMaa Krupa BuildconDue Dec 2027——
Mone Mixed ApartmentPratibha Rajendra MoneDue Jul 2027, extended 4 mo——
Shiv - Maa Bhagwati ParkShivurja Builders Private LimitedDue Jul 2029, extended 4 mo——
Shree Ganesh HeightsGoldstar BuildersDue Jul 2029, extended 4 mo——
Shree Mateshwari VishwaKetan Santu ChakaneDue Apr 2029, extended 4 mo——
Sky53Sky53Due Oct 2027, extended 4 mo——
Premkusum Appartment Co-Operative Housing Society LimitedKtg AssociatesDue Apr 2028, extended 4 mo——
Venus TriumphVenus Baburao Wani5 mo late——
Aishwarya HeightsChandrakant Nivrutti SonawaneDue Feb 2028, extended 4 mo——
Roongta Eminence ApartmentShree Tirumala BuildconDue Jul 2030, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology