7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Dwarka ResidencyGovinda ConstructionCompleted—30%
Fortune ResidencyMohan Sukdeo KakalisCompleted—50%
Kmc Business ParkKmc BuildconDue Apr 2027, extended 4 mo—10%
Laxmi VandanOsara Developers2 yrs 2 mo late——
Shivswami HeightS P ConstructionCompleted—83%
Sky OneOm Sai Om BuildersDue Apr 2027, extended 4 mo—25%
Aakar NakshatraAakar BuildconCompleted—45%
Amar ApexAmar VenturesCompleted, extended 3 mo——
Gokul 5Gokul InfrastructureCompleted—91%
Kanak ResidencyDeepali Sandeep JainCompleted——
Mahadeo AppartmentMahadeo ConstructionsCompleted—100%
Sainath Residency Co Operative Housing Society Limited NasikSainath Residency Co Operative Housing Society Limited NasikCompleted——
Shreeji InfiniaShreeji Life SpaceCompleted—76%
Suyojit Viridian Vallis Phase-III Sector G4 CommercialSun Infrastructures Pvt LtdDue Dec 2026, extended 3 yrs—45%
Swaroop ResidencyShree Construction CompanyCompleted——
Tulsi Kunj ApartmentTulsi ConstructionCompleted—40%
Yogeshwar NiwasYogeshwar BuildtechCompleted—65%
Dream PlazaRehan Ahmed Iftekhar Ahmed ShaikhCompleted—10%
Kalapurnam ParkDinkar Murlidhar PaldeDue Nov 2026, extended 4 mo——
Manisha ApartmentOm Sai DevelopersCompleted—100%
New Jasmine Apartment Co Op Hsg SocR K Engineers & DevelopersCompleted—68%
Pride Laxmi RamnaAditya DevelopersDue Dec 2026—53%
Yash ApartmentSonali Bharat PawarCompleted—100%
AmrutyogYogesh Janardan NagmotiCompleted——
OzoneSure Deal Marketing Pvt LtdCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology