7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shivdhara HeightsShreeram Builders And DevelopersCompleted——
Shree Ganesh NakshtraSiddhivinayak DevelopersDue Dec 2027, extended 3 yrs—80%
Shree Paras Empire GrandDeepak Nemichand ModiCompleted—33%
Sohan City Phase 2Sagar Sohanlal Bhandari11 mo late——
Vaishnavi Krupasindhu ParkVaishnavi Builders1 yr 11 mo late——
Vakratund AnnexVijayamrut BuildersDue Apr 2027, extended 4 mo—40%
Yashoda BlissAnubhooti Infrastructures Pvt Ltd1 yr 11 mo late—44%
Aaradhya ResidencyAp ConstructionCompleted——
Dream Valley ApartmentHardik DevelopersCompleted——
Iconic Business Center DwarkaBagad PropertiesDue Feb 2030, extended 4 mo——
MadhavbagMonali Tushar Aher1 yr 11 mo late—60%
Prima Casa ApartmentCasa Costruzione InfratechCompleted——
Rehmat ApartmentParvin Gamir ShaikhCompleted—42%
Rushiraj Radiance ApartmentJhala InfratechCompleted—67%
Rushiraj Zodiac ApartmentJhala InfratechCompleted—61%
Sai AshaJay Developers2 yrs 8 mo late—11%
Shivshakti HeightsNeha Bhavani DubeyCompleted—82%
Siddhesh ResidencyAkash Dinesh ChordiyaCompleted—80%
Suyojit Viridian Vallis Sector C And ISun Infrastructures Pvt Ltd3 yrs 8 mo late——
Vrundavan AvenueBhushan Nitin BagnarCompleted—50%
Balaji PrideOm DevelopersCompleted—45%
GruhamDeepak Ramchandra BagadCompleted—42%
Sharada HeightsDishant Manohar Lohar1 yr 1 mo late—80%
Siddhivinayak HeightsShantanu Pratapsinh PatilCompleted—74%
The ExchangeViraj Estates Pvt. Ltd. & OthersCompleted—31%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology