7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
SamarpanRenuka InfrastructuresDue Apr 2030, extended 4 mo——
Garden ResidencyRamesh Sakharam AvhadDue Jul 2029, extended 4 mo——
Vedant SignatureVedant ConstructionDue Apr 2030, extended 4 mo——
Amr SerenityA M R Developers Private LimitedDue Jul 2028, extended 4 mo——
Soha FatemaMajestic BuildersDue Apr 2031, extended 4 mo——
Ambrish SocietyShree Builders And DevelopersDue Apr 2031, extended 4 mo——
Shree GurudarshanNirmiti InfrastructureDue Jul 2028, extended 4 mo——
Sai Umang HeightsSai Umang InfraDue Apr 2028, extended 4 mo——
Samarth EmeraldVinayaka BuildersDue Apr 2031, extended 4 mo——
Om GalaxyOm Sai ConstructionDue Jul 2030, extended 4 mo——
Shree Datta PlazaShree Gurudatta BuildersDue Jul 2030, extended 4 mo——
Shyam B TownCrestline Buildtech Pvt LtdDue Apr 2031, extended 4 mo——
Shri Ganesh HeightsShree Ganesh ConstructionDue Apr 2034, extended 4 mo——
DwarkamaiSaumya BuildconDue Apr 2028, extended 4 mo——
Shree Ganesh InsigniaSonali RealtyDue Apr 2030, extended 4 mo——
Span CenterSpan DevelopersDue Aug 2029, extended 4 mo——
Ayodhya EmpireAyodhya DevelopersDue Jul 2029, extended 4 mo——
East ZoneS. S. DevelopersDue Apr 2031, extended 4 mo——
Nilanjan VastuNayan Sanjaysheth BhavsarDue Apr 2029, extended 4 mo——
City SquareShrinivas BuildtechDue Apr 2031, extended 4 mo——
Daksh MarvelleDaksh RealtyDue Dec 2027, extended 4 mo——
Devrang GreensOm DevelopersDue Jul 2030, extended 4 mo——
Krushnakunj HeightsHaridarshan DevelopersDue Jul 2029, extended 4 mo——
Madhav HomesMadhav BuildersDue Apr 2030, extended 4 mo——
Shubh Aarambh - Phase 2Shubhshree InfratechDue May 2031, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology