Deedo IDDL-NSK-NASHIK7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
7 in 10 registrations run late here
4,253 MahaRERA registrations in Nashik and the places within it
376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nashik
4,202 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| SamarpanRenuka Infrastructures | Due Apr 2030, extended 4 mo | — | — |
| Garden ResidencyRamesh Sakharam Avhad | Due Jul 2029, extended 4 mo | — | — |
| Vedant SignatureVedant Construction | Due Apr 2030, extended 4 mo | — | — |
| Amr SerenityA M R Developers Private Limited | Due Jul 2028, extended 4 mo | — | — |
| Soha FatemaMajestic Builders | Due Apr 2031, extended 4 mo | — | — |
| Ambrish SocietyShree Builders And Developers | Due Apr 2031, extended 4 mo | — | — |
| Shree GurudarshanNirmiti Infrastructure | Due Jul 2028, extended 4 mo | — | — |
| Sai Umang HeightsSai Umang Infra | Due Apr 2028, extended 4 mo | — | — |
| Samarth EmeraldVinayaka Builders | Due Apr 2031, extended 4 mo | — | — |
| Om GalaxyOm Sai Construction | Due Jul 2030, extended 4 mo | — | — |
| Shree Datta PlazaShree Gurudatta Builders | Due Jul 2030, extended 4 mo | — | — |
| Shyam B TownCrestline Buildtech Pvt Ltd | Due Apr 2031, extended 4 mo | — | — |
| Shri Ganesh HeightsShree Ganesh Construction | Due Apr 2034, extended 4 mo | — | — |
| DwarkamaiSaumya Buildcon | Due Apr 2028, extended 4 mo | — | — |
| Shree Ganesh InsigniaSonali Realty | Due Apr 2030, extended 4 mo | — | — |
| Span CenterSpan Developers | Due Aug 2029, extended 4 mo | — | — |
| Ayodhya EmpireAyodhya Developers | Due Jul 2029, extended 4 mo | — | — |
| East ZoneS. S. Developers | Due Apr 2031, extended 4 mo | — | — |
| Nilanjan VastuNayan Sanjaysheth Bhavsar | Due Apr 2029, extended 4 mo | — | — |
| City SquareShrinivas Buildtech | Due Apr 2031, extended 4 mo | — | — |
| Daksh MarvelleDaksh Realty | Due Dec 2027, extended 4 mo | — | — |
| Devrang GreensOm Developers | Due Jul 2030, extended 4 mo | — | — |
| Krushnakunj HeightsHaridarshan Developers | Due Jul 2029, extended 4 mo | — | — |
| Madhav HomesMadhav Builders | Due Apr 2030, extended 4 mo | — | — |
| Shubh Aarambh - Phase 2Shubhshree Infratech | Due May 2031, extended 4 mo | — | — |
Localities in Nashik
- Nashik1,372 projects
- Nashik (M Corp.)1,251 projects
- Nashik301 projects
- Aanandwali94 projects
- Deolaligaon67 projects
- Nashik Road67 projects
- Satpur56 projects
- Jail Road55 projects
- Deolali (Cb)50 projects
- Makhmalabad45 projects
- Pathardi37 projects
- Adgaon30 projects
All 103 localities
- Nashik Shiwar29
- Sinnar(M Cl)29
- Igatpuri (M Cl)28
- Vihitgaon28
- Kamatwade25
- Mhasrul25
- Bhagur Rural24
- Indiranagar24
- Sansari24
- Pimpalgaon Baswant23
- Chehedi Bk22
- Ozar (Ct)22
- Chandshi21
- Sinnar21
- Sinnar16
- Malegaon (M Corp.)15
- Wadala Shivar15
- Igatpuri14
- Gangapur13
- Chunchale10
- Dasak10
- Dindori10
- Jalalpur9
- Shinde9
- Belatgavhan8
- Palse8
- Ambad Khurd7
- Kasbe Vani7
- Lasalgaon7
- Panchak7
- Pimprisado7
- Bhagur (M Cl)6
- Gondedumala6
- Govardhan5
- Niphad5
- Satana4
- Malegaon3
- Niphad3
- Saikheda3
- Shramik Nagar3
- Trimbakeshwar3
- Yeola3
- Chandvad (Ct)2
- Dindori2
- Ghoti Bk. (Ct)2
- Girnare2
- Kawanai2
- Manmad (M Cl)2
- Naigaon2
- Nilgavhan2
- Ozar Gaon2
- Sangameshwar (Ct)2
- Saradwadi2
- Shivaji Nagar2
- Soyagaon (Ct)2
- Trimbakeshwar2
- Agartakli1
- Ashok Nagar1
- Behed1
- Beladgavhan1
- Borivali1
- Deola1
- Deshwandi1
- Gaulane1
- Gitakunj1
- Jaulke(Dindori)1
- Kasbe Sukene1
- Khambale1
- Madsangvi1
- Maparwadi1
- More Nagar1
- Mungsara1
- Naikwadi1
- Nandadgaon1
- Nandgaon1
- Pakhal Road1
- Pardevi1
- Pimpalgaon Bahula1
- Pimpalgaon Garudeshwar1
- Pimpalgaon Ketaki1
- Pimpalgaon Najik (Ct)1
- Satpur Colony1
- Surgana1
- Talegaon1
- Talegaon(Dindori)1
- Titoli1
- Trimbak (M Cl)1
- Umarane1
- Vilholi1
- Vinchur1
- Wasali1
Other districts
Most active promoters
- Roongta Homes Llp26 projects
- Jay Developers13 projects
- Kbc Global Limited12 projects
- Sanklecha Construction Private Limited11 projects
- Shah Builders And Developers11 projects
- Nashik Housing And Area Development Board10 projects
- Shreeji Life Space10 projects
- Deepak Kalyanji Chande9 projects
- Govinda Construction9 projects
- Sun Infrastructures Pvt. Ltd9 projects
Nashik, in questions
How many projects in Nashik run late?
7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology