7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Bhagwati ApartmentNew Swamiraj ConstructionDue Jun 2028, extended 4 mo——
Shree Sham ApartmentShree Sham Builders And DevelopersDue Jul 2029, extended 4 mo——
Pm1220002503052Patil Epitome Pvt LtdDue Apr 2030, extended 4 mo——
Nashik Business Park Phase 2Santosh Eknath ChakankarDue Apr 2032, extended 4 mo——
Shripad AvenueShriram Builders And DevelopersDue Jul 2030, extended 4 mo——
Inayat CityInayat Builders and DevelopersDue Apr 2031, extended 4 mo——
Alaknanda ApartmentRam ConstructionsDue Apr 2031, extended 4 mo——
Balaji HeightsGeeta DevelopersDue Apr 2031, extended 4 mo——
Halpani EnclaveHalpani BuildconDue May 2031, extended 4 mo——
Swami SankulSwami BuildconDue Apr 2029, extended 4 mo——
Vishrant CHS LtdKalash InfrastructureDue Apr 2030, extended 4 mo——
Yashoda's Maheshwar KunjShree Jyoti InfraDue Apr 2030, extended 4 mo——
Viraj SattvaViraj Estates Private LimitedDue Apr 2030, extended 4 mo——
Bramhand ApartmentShree Builders And DevelopersDue Apr 2030, extended 4 mo——
Govinda HarmonyRadhe DevelopersDue Apr 2029, extended 4 mo——
Manohar EnclaveMonarch ConstructionsDue Apr 2031, extended 4 mo——
Rajas ResidenceShiva InfraDue Apr 2029, extended 4 mo——
Rathod ResidencySiddhant DevelopersDue Apr 2029, extended 4 mo——
Sai Raj ResidencySai Ganraj DevelopersDue Jul 2029, extended 4 mo——
Shree Vyankatesh PrideShree Siddhi ConstructionsDue Apr 2029——
Shri Ganesh VandanDilip Babulal WaniDue Sep 2028, extended 4 mo——
Ganraj SankulTrident DevelopersDue Jul 2029, extended 4 mo——
Yugandhar ApartmentM.k.groupsDue Apr 2029, extended 4 mo——
Amrut Kalash ApartmentSwastik EstatesDue Apr 2030, extended 4 mo——
Ganga Residency Building BGajsiddhi DevelopersDue Apr 2031, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology