Completion was pushed back 4 months, to Aug 2029; no MahaRERA orders on record; 0% of its units are booked.

Nashik (M Corp.), Nashik 422001 · by Span Developers

DeliveryExtended 4 moPromised Apr 2029 · now due Aug 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 110 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Aug 2029

  • This projectRegistered 18 Apr 2026, completion promised 1 Apr 2029, revised to 1 Aug 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPC1220002600170
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PC122000260017018 Apr 20261 Apr 20291 Aug 2029Span DevelopersProject page
Documents31

1 document held by Deedo, 30 filings listed on MahaRERA's project page

Registration certificate

Finance

  • GSTIN DocumentAA270522071730E_RC03062022.pdf · uploaded 6 Mar 2026Source
  • PAN CardPAN - SPAN Deve..pdf · uploaded 6 Mar 2026Source
  • OthersAnnexure A - Prashant Avhad.PDF · uploaded 7 Mar 2026Source
  • OthersAnnexure A - Ram Patil.PDF · uploaded 7 Mar 2026Source
  • OthersAnnexure A - Rhushikesh Gaidhani.PDF · uploaded 7 Mar 2026Source
  • OthersAnnexure A - Shweta Darade.PDF · uploaded 7 Mar 2026Source
  • OthersAnnexure A - Sonal Patil.PDF · uploaded 7 Mar 2026Source
Show all 31 documentsShow fewer documents

Finance

  • OthersAnnexure A - Tushar Bora.PDF · uploaded 7 Mar 2026Source
  • OthersCERSAI report declaration - No Security Interest.PDF · uploaded 7 Mar 2026Source
  • OthersCERSAI_Search_Report.pdf · uploaded 7 Mar 2026Source

Legal

  • OthersEncumrances - Legal.PDF · uploaded 23 Feb 2026Source
  • Declaration Form BDeclaration in Form B.pdf · uploaded 23 Feb 2026Source
  • Declaration Form BFinal Purchase Deed of Both Plots.pdf · uploaded 23 Feb 2026Source
  • Declaration Form BLegal Title Report_compressed.pdf · uploaded 5 Mar 2026Source
  • OthersPurchase Deed 608 Vakil Wadi_Pg 1 to 25.pdf · uploaded 7 Mar 2026Source
  • OthersPurchase Deed 608 Vakil Wadi_Pg 26 to 49.pdf · uploaded 7 Mar 2026Source
  • OthersPurchase Deed 608C vakil wadi_Pg 1 to 24.pdf · uploaded 7 Mar 2026Source
  • OthersPurchase Deed 608C vakil wadi_Pg 25 to 48.pdf · uploaded 7 Mar 2026Source
  • OthersNo Daviation Agreement.PDF · uploaded 7 Mar 2026Source
  • OthersNo Daviation Allotment.PDF · uploaded 7 Mar 2026Source

Planning Authority

  • Documentg7Vrf2L9lCSALE_DEED_.pdf · uploaded 6 Mar 2026Source
  • DocumentCert_B_581113_419VfngXSign.pdf · uploaded 6 Mar 2026Source
  • DocumentQpvTOfUeFaEXTRACT_PLOT_7_12_.pdf · uploaded 6 Mar 2026Source
  • Document1764386415_NMCB-25-61376_R0.pdf_2_39DSE_Sign.pdfSign.pdf · uploaded 6 Mar 2026Source
  • Document1764386415_NMCB-25-61376_R0.html · uploaded 6 Mar 2026Source

Technical

  • DocumentAPPROVED PLAN ORIGINAL.pdf · uploaded 23 Feb 2026Source
  • DocumentAPPROVED PLAN ORIGINAL.pdf · uploaded 23 Feb 2026Source
  • DocumentDeclaration Cum Undertaking Annexure - A.PDF · uploaded 7 Mar 2026Source
  • OthersFormat D.pdf · uploaded 7 Mar 2026Source
  • OthersAPPROVED PLAN ORIGINAL 1.pdf · uploaded 18 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS No 608/C/2/1, CTS No. 608/C/2/2

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
—110 units in all
Address
Vakil wadi, M G ROADPIN 422001
Village
Nashik (M Corp.), Nashik taluka
Land area for this project
926 sq m (9,969 sq ft)
Permissible built-up area
4,134 sq m (44,493 sq ft)
Sanctioned built-up area
3,959 sq m (42,610 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS No 608/C/2/1CTS No. 608/C/2/2

Land as published on MahaRERA's project page

plot_no - city_survey_gut_no CTS NO. 608/C/2/2,CTS NO. 608/C/2/1 final_plot_no - sector_no - mauje NASHIK GAOTHAN road_street 9.00 society RESI. AND COMM.

Boundaries

North
Property named Balwant Plaza
South
Property named Manorama Arcade and CTS No. 609/A
East
V.T.S. Gut No. 602/3
West
Vakilwadi Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking110 units

110 units registered

— · 110 units
TypeCarpet areaUnits
——110

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGanesh Sonawane—
Chartered accountantAnuj Bafna—
EngineerApurv Keshvrao Patil—
EngineerBhanuvilas Bhawsar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Nashik (M Corp.)

All 1,251 projects in Nashik (M Corp.) · Compare Span Center with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology