7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Para AvenueKishan PokarCompleted——
Siddhesh HeightsSiddhesh DevelopersCompleted—20%
Avadh EliteAkshar BuildersCompleted—56%
Aarambh EliteKothari Housing CompanyDue Jun 2027—15%
Hariom ParadiseHariom GroupCompleted—25%
Sai Srushti Phase IIYogesh Kailas Harak1 yr 11 mo late—76%
Leela GalaxyManish Gulabrao Mhaske1 yr 11 mo late——
Suman ApartmentMilind Nivrutti MankarCompleted——
Shree Shankar Apartment Wing F And GShree Shingar Constructions Private Limited1 yr 5 mo late——
Balaji ExcellencyPrasad Gangadhar VyavahareCompleted——
Balaji VillageKalantri And Musale Realcon LLPDue Apr 2027, extended 4 mo—75%
Hari Darshan Heights ApartmentVaibhav DevelopersCompleted——
Jagruti Co-operative Housing Society Ltd.Moulik Jitendra ShahCompleted—63%
Lotus ResidencyLotus Infra8 mo late——
Rajyog HeightsVasundhara Yogesh GosaviDue Dec 2026, extended 2 yrs——
Sai Harsh AvenueA Cube B Buildcon4 yrs 3 mo late——
Sai SrushtiShramsaflya Buildcon1 yr 8 mo late——
Sai VedHari Vyankatesh Developers Proprietor Tushar Sharad Kumar11 mo late—82%
Shivalik SynergyYogeshwar InfraDue Apr 2027, extended 4 mo——
Shreedatta PresidencyShree Datt BuildersDue Apr 2027, extended 4 mo—5%
Shree UdayRam ConstructionsCompleted—39%
Suman SymphonySuman Leela Associate1 yr 11 mo late——
Swaroop IconSwaroop DevelopersCompleted—74%
Yashoda TridentExcellers Buildcon8 mo late——
Arohi HeightsRohini Subhash PawarCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology