7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Aurum ApartmentLahoti Builders And Developers Proprietor Kapil Shyamsundar LahotiCompleted——
Bhagwati PlazaShubham DevelopersDue Jul 2027, extended 4 mo——
Chaudhari IconRahul Dilip ChaudhariCompleted, extended 1 yr—76%
Daulat HeightsGulab Doulat MaliCompleted—67%
Durvankur GardenNarendra A Jadhav & Jaywant B Yeola2 yrs 8 mo late——
Hariom EliteHariom GroupCompleted——
Krishna VillaKrishna Constructions2 yrs 8 mo late—71%
Lambodar Heights ApartmentLambodar DevelopersCompleted—17%
MarutinandanUsha Devi Ashok Hisaria2 yrs 8 mo late——
Natures DivineDivine SpaceCompleted—100%
Panchdev Pooja Row HouseKajalben Sanjaybhai SuraniCompleted——
Radha NagariDeepak Infra And Homes Private LimitedDue Dec 2028——
Sainath HeightsDhruved ConstructionCompleted—20%
Sai Shraddha ApartmentSai Prasad Builders And DevelopersCompleted—29%
Shree Ganesh ApartmentPrabhakar Murlidhar Kathe1 yr 7 mo late——
Shukla Business TowerDeal ConstructionDue Aug 2029, extended 4 mo——
Siddhi ParadiseVasturang BuildconCompleted—13%
Siddhivinayak ParkSiddhivinayak Constructions11 mo late——
S K ParadiseNilesh Suresh GuruleDue Apr 2027, extended 4 mo—5%
SPACE WORTH DEVELOPERS Meenakshi PrideVaibhav Deepak DeoreCompleted—27%
The Gracious ParkSurya ConstructionCompleted—100%
The Santosh Business SquareShri Krishna Vaibhav Developers5 mo late——
Yash HeightsDeeliprao Daulatrao DeoreCompleted——
Ambika HarmonyAmbika BuildconCompleted, extended 1 yr——
BALAJI SerenityVaishnav ConstructionsCompleted—82%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology