7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Gangashakun Co Op Hos SocietyAdinath BuildersCompleted—45%
Pushkar Co-Op. Hsg. Soc. Ltd.Raviraj Buildtech2 yrs 9 mo late—17%
Yamuna PrideYamuna ConstructionsDue Apr 2028, extended 4 mo—20%
Aura DreamSai ConstructionsCompleted—47%
Dhruv ResidencyYogita Rushikesh More2 yrs late—53%
GruhyogPatil Shah HousingDue Apr 2031——
Guruashish ApartmentShrinidhi DevelopersCompleted, extended 5 mo—50%
Indu PlazaValu Shivram PalveCompleted——
Krushnaprem HeightsPramila Balasaheb KothuleCompleted—47%
Mirage TowerUnity ConstructionsCompleted—62%
Revati Sunanda ApartmentRevati Infra EngineersCompleted—32%
Roongta Exquisite ApartmentRoongta Landmarks LLPDue Jan 2027, extended 4 mo—11%
Roongta Preciso ApartmentRoongta Homes LLPCompleted—64%
Shilp AlaskaDevsan Infrastructure Private LimitedDue Oct 2029, extended 4 mo—26%
AanganAbh Developers Private Limited2 yrs 11 mo late——
HallmarkHighland Builders And DevelopersDue Dec 2027, extended 2 yrs—8%
Rajlaxmi HeightRajlaxmi Construction1 yr 8 mo late——
Shree Atharva PrideManoj Prataprao DeshukhCompleted—51%
Roongta Ashok Vihar ApartmentShree Chawo Sati Builders Private LimitedCompleted—21%
Swastik ApartmentShreeraj BuildersCompleted——
Global VilleShraddha InfraDue Jul 2027, extended 4 mo—15%
Mangal Murti ApartmentPrafull Shankarrao Ahire3 yrs 8 mo late—78%
Vatavruksh HeightsL T Infrastructure Proprietor Tejpal Khyaliram VigCompleted—47%
Aura ResidencyVivek Kailas Patil Prop Jupiter BuildconCompleted—36%
Business CubeKasturi Builders And Developers8 mo late——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology