7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shabina ParkTamboli BuildtechDue May 2027, extended 4 mo——
Shiv OrchidLandmark infraCompleted——
Shivtirth HeightsMillennium DevelopersDue Apr 2028, extended 4 mo—29%
Shubham HeightsManda Bhimrao PatekarCompleted—33%
Sunshine EliteSai Ram ConstructionCompleted—79%
Swami CharanSwami BuildconCompleted—50%
Vraj Metropolis NorthShree Infra SpaceDue Apr 2029, extended 4 mo—7%
Vrundavan City Pride MallVrundavan Builders1 yr 8 mo late—18%
Ganesha PrideVardhaman Suvalal LodhaCompleted——
Infinity HeightsD W Associates2 yrs 4 mo late—29%
Mahadeo ShrushtiMahadeo BuildconCompleted——
Parth LokeshK B Estate8 mo late——
Adiva BunglowsTarachand Devisahay Gupta1 yr 8 mo late——
Qasrul Khulafa 2Vijaya ConstructionsDue Jul 2027, extended 4 mo——
Shyam AnandHeena Satishbhai ChavdaCompleted—64%
Shyam ShubhMonika Jaykumar Vala10 mo late—38%
Vandemataram ResidencyVandemataram Buildcon2 yrs 5 mo late—33%
Dream Nest Peak OneShubham Suvalal DhadiwalCompleted, extended 5 mo—33%
Jadhav Park-2Nandkumar Bhagirath JadhavDue Apr 2028, extended 4 mo—14%
Mangalmurti ApartmentPranjal Nalin Chandak2 yrs 9 mo late——
Omkar HeightsKothawale Patil Builders And Developers Pvt. Ltd.Completed——
Perfect Rama ResidencyPerfect BuildwellCompleted——
Regant PlazaRakhee PapnejaCompleted—11%
Saubhagya PrideAjinkya Pravin Munot1 yr 9 mo late——
Shivram ResidencyMaheshwar EnterprisesCompleted—85%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology