7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Trimbak SankulSarathi Construction CompanyDue Apr 2027, extended 4 mo——
VasantpushpaKtg AssociatesCompleted—25%
Vishwamangal Co-operative Housing Society Ltd. NashikVishwamangal Co-operative Housing Society Ltd. Nashik11 mo late—97%
Vrindavan DhamRajmudra ConstructionsDue Apr 2029, extended 4 mo—8%
Samarth HeightsAtul Vilas KankateCompleted——
Tirumal Co-Op. Hsg. Soc.ltdJ And B Builders2 yrs 9 mo late—9%
Yashoda MiraclePawar PropertiesDue Mar 2027——
Blossom ApartmentKanaklaxmi Developers1 yr 8 mo late—11%
Heramb ResidencyDinesh Eknath KhandreCompleted—75%
Prime ArchadeFiroz Alam Ansari Prop Of Prime Developers1 yr 11 mo late—50%
Rutica HeightsRutica Infra LLPCompleted—56%
Samruddhi TowerSamruddhi InfrastructuresDue Jul 2027, extended 4 mo—39%
Sarthak HeightsSarthak Builders And DevelopersCompleted—75%
Shivdeep ResidencyShivpooja BuildconCompleted——
Shivneri CrystalSiddhivinayak Infra2 yrs 5 mo late——
Shiv Suman ResidencyS K ConstructionCompleted, extended 6 mo—92%
Shree Sadguru Dhage Maharaj Co-operative Housing Society Ltd. NashikAmol Shashikant AhirraoDue Apr 2027, extended 4 mo—84%
Shri Ganesh NandanDilip Babulal Wani8 mo late—9%
Shri Ram Kunjshree balaji developers5 mo late——
Swapna HeightsSwapnpurti BuildersDue Apr 2027, extended 4 mo——
Ayesha EliteSupreme RealtyCompleted—83%
Bhagirath ParkShree Construction1 mo late—58%
Devi Darshan Row HousesDales Realtors11 mo late——
Fhabiya ManzilAtiya Irsad FarooquiCompleted—88%
Gokulvan ApartmentAllwin ConstruwellDue Jul 2027, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology