Qasrul Khulafa 2

Certificate Signed

Nashik 422009 |Promoter: Vijaya Constructions

7 Feb 2023Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
2Buildings
45Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
2BHK, 3BHK, Shop45 units in all
Address
Survey No. 9/1 to 9/5/2/1 to 6, PlotNo. 1 to 3, Ashoka Marg, Wadala ShiwarPIN 422009
Designated bank account
76
Developed in phases
Yes

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 Feb 2023
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000492967 Feb 202331 Mar 202731 Jul 2027Vijaya ConstructionsProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building A524
Building B521

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 45 units booked (0%), as the promoter reported to MahaRERA

2BHK · 28 units3BHK · 14 unitsShop · 3 units
BuildingTypeCarpet areaUnitsBooked
Building A2BHK68.31 sq m · 735 sq ft140
Building A3BHK105.73 sq m · 1,138 sq ft70
Building AShop19.95 sq m · 215 sq ft10
Building AShop23.1 sq m · 249 sq ft10
Building AShop27.43 sq m · 295 sq ft10
Building B2BHK83.76 sq m · 902 sq ft70
Building B2BHK88.76 sq m · 955 sq ft70
Building B3BHK77.4 sq m · 833 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 103 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardvijaya pan.pdf · uploaded 22 Nov 2022Source

Legal

  • Legal Title reportLEGAL TITLE REPORT.pdf · uploaded 22 Nov 2022Source
  • Declaration Form B5 Affidavit.pdf · uploaded 22 Nov 2022Source
  • Declaration Form BAffidavit_Declaration.pdf · uploaded 21 Apr 2025Source

Migrated

  • 1 PAN Cardvijaya pan.pdf · uploaded 22 Nov 2022Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 22 Nov 2022Source
  • 1 a Details of encumbrances concerned to Finance11 Declaration on Encrumbances.pdf · uploaded 22 Nov 2022Source
Show all 104 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to Legal11 Declaration on Encrumbances.pdf · uploaded 22 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan0126- BUILDING PLAN_compressed (2).pdf · uploaded 22 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan0127- BUILDING PLAN_compressed.pdf · uploaded 22 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted development9 Commencement Certificate.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration about Commencement Certificate10 Declaration on commencement certificate.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration in FORM B5 Affidavit.pdf · uploaded 22 Nov 2022Source
  • 1 Proforma of Agreement for saleSALE AGREEMENT.pdf · uploaded 22 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)Rera -Land layout.pdf · uploaded 24 Nov 2022Source
  • 1 CERSAI detailsCERSAI DECLARATION.PDF · uploaded 24 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F 3.PDF · uploaded 24 Nov 2022Source
  • 1 Proforma of Allotment lettervijaya const_compressed.pdf · uploaded 24 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DECLARATION.PDF · uploaded 24 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION PROFORMA.pdf · uploaded 24 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION AFS DECLARATION.PDF · uploaded 24 Nov 2022Source
  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCE FINANCE.pdf · uploaded 16 Jan 2023Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCE FINANCE.pdf · uploaded 16 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsASHUTOSH DECLARATION.PDF · uploaded 16 Jan 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsPRANAV DECLARATION.PDF · uploaded 23 Jan 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scan20231125162627.pdf · uploaded 25 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(05_08_23).pdf · uploaded 19 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(15_10_23).pdf · uploaded 19 Dec 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(16_01_24).pdf · uploaded 19 Dec 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(28_05_24).pdf · uploaded 19 Dec 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(15_07_24).pdf · uploaded 19 Dec 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(20_10_24).pdf · uploaded 19 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1(16_04_23).pdf · uploaded 19 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(Dec 23).pdf · uploaded 19 Dec 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(Sept 24).pdf · uploaded 19 Dec 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(June 24).pdf · uploaded 19 Dec 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(June 23).pdf · uploaded 19 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(March 24).pdf · uploaded 19 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(Sept 23).pdf · uploaded 19 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(March 23).pdf · uploaded 19 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(14_04_23).pdf · uploaded 19 Dec 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(21_10_24).pdf · uploaded 19 Dec 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(18_07_24).pdf · uploaded 19 Dec 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(31_05_24).pdf · uploaded 19 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(16_01_24).pdf · uploaded 19 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(18_10_23).pdf · uploaded 19 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(08_08_23).pdf · uploaded 19 Dec 2024Source
  • 1 Other – TechnicalCommencement Certificate.pdf · uploaded 19 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5(2022-23).pdf · uploaded 19 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5(2023-24).pdf · uploaded 19 Dec 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 20 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 20 Dec 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan0237_compressed.pdf · uploaded 20 Dec 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentscan0239_compressed.pdf · uploaded 20 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form -2A (Marsch 23).pdf · uploaded 23 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (10_01_25).pdf · uploaded 8 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3(Dec 24).pdf · uploaded 8 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2(10_01_25).pdf · uploaded 8 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold unsold disclosure.pdf · uploaded 8 Apr 2025Source
  • 1 Declaration in FORM BAffidavit_Declaration.pdf · uploaded 21 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2a.pdf · uploaded 21 Apr 2025Source
  • Form 1Form 1 march 25.pdf · uploaded 30 Oct 2025Source
  • Form 2Form2 March 25.pdf · uploaded 30 Oct 2025Source
  • Form 3Form 3 March 25.pdf · uploaded 30 Oct 2025Source
  • Disclosure of Sold and Booked InventorySigned Sold unsold Inventory(March 2025).pdf · uploaded 30 Oct 2025Source
  • Form 5 (FY 2024-2025)Form 5(2024-25).pdf · uploaded 30 Oct 2025Source
  • Form 2A (FY 2024-2025)Form 2a.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 1Form 1(June 2025).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 1Form 1(September 2025).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 1Form 1(December 2025).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 2Form 2 new(June 25).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 2Form 2 new(Sept 2025).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 2Form 2 new(Dec 2025).pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 3Form 3(June 25) new.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 3Form 3 (September 25) new.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 3Form 3(December 25) new.pdf · uploaded 1 Jun 2026Source
  • Withdrawal Update Form 1Form 1(March 26).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form 2 (March 26).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3(March 26) new.pdf · uploaded 8 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A new.pdf · uploaded 29 Jun 2026Source

Technical

  • Documentscan0126- BUILDING PLAN_compressed (2).pdf · uploaded 22 Nov 2022Source
  • Documentscan0127- BUILDING PLAN_compressed.pdf · uploaded 22 Nov 2022Source
  • DocumentRera -Land layout.pdf · uploaded 24 Nov 2022Source
  • Other – TechnicalCommencement Certificate.pdf · uploaded 19 Dec 2024Source
  • DocumentBuilding Plan.pdf · uploaded 20 Dec 2024Source
  • Documentscan0237_compressed.pdf · uploaded 20 Dec 2024Source
  • Documentscan0239_compressed.pdf · uploaded 20 Dec 2024Source

Technical (Architect)

  • DocumentForm 1(05_08_23).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1(15_10_23).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1(16_01_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1(28_05_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1(15_07_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1(20_10_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 1 (10_01_25).pdf · uploaded 8 Apr 2025Source
  • DocumentForm 1(March 26).pdf · uploaded 8 Jun 2026Source

Technical (Engineer)

  • DocumentForm 2(08_08_23).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(18_10_23).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(16_01_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(31_05_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(18_07_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(21_10_24).pdf · uploaded 19 Dec 2024Source
  • DocumentForm 2(10_01_25).pdf · uploaded 8 Apr 2025Source
  • DocumentForm 2 (March 26).pdf · uploaded 8 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik, Nashik taluka

Survey, CTS, gat or plot numbers

PlotNo. 1 to 3Survey No. 9/1 to 9/5/2/1 to 6

Boundaries

North
Plot
South
Road
East
Road
West
Plot

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGaneshkumar Wable—
ArchitectRahul Rathi—
Chartered accountantDevendra Belan—
EngineerChandrakant Kaule—
EngineerMilind Rathi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology