Skip to content
Deedo home
Menu

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Nashik · Nashik
Registration
RERA numbers
PromoterVijaya Constructions
Status on MahaRERACertificate Signed
Registered on7 Feb 2023
Delivery
Promised completion31 Mar 2027
Revised completion31 Jul 2027
Delay vs RERA date+4 monthsrevised completion date
Extension certificates0
Size
Project land area—
Buildings on record2
Units45
Units booked00% of units
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA13 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology