7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Abh Nature TalesAbh Developers Private LimitedDue Apr 2027——
Dattaraj ApartmentB K BuildersCompleted—41%
MadhubanGajra AssociatesDue Apr 2028, extended 4 mo—4%
MuktanganVaishnav ConstructionsDue Apr 2028, extended 4 mo—2%
Shree Balaji ParkShree Balaji AssociatesCompleted—31%
Shree Eknath HeightsShree Eknath BuildconCompleted——
Sohan City Phase 2 LasalgaonSagar Sohanlal BhandariDue Apr 2027, extended 4 mo—83%
Sri Samartha AanganSri Samartha AssociatesDue Jun 2027——
The RisingVishal Krishnadeo DesaleDue Dec 2028, extended 4 mo——
Shreeji ElevateShreeji Life SpaceDue Apr 2029, extended 4 mo—12%
Shyam SignetParshwanath Buildcon5 mo late—29%
The Privilege HomesSayali Subhash KaleCompleted—16%
Akruti Co-operative Housing Society LimitedSpiti Construction Private LimitedCompleted—64%
Deolali Meadows D WingAtb Samarth LLP11 mo late——
Faiz-E-Rasul ParkShaukatali Ismail GhaswalaDue Mar 2028——
Malpani CentralAshish Hemant MalpaniDue Apr 2029, extended 4 mo——
Noori TowerF. K. Construction Proprietor Mr. Farooque Khan S. PathanDue Aug 2027, extended 4 mo——
Pushkraj NakshatraPushkraj Buildcon5 mo late—26%
Aashray ResidencyShrinath RealtyDue Apr 2028, extended 4 mo—7%
Classic ParadiseSingh ConstructionsDue Apr 2027, extended 4 mo—32%
Kamdhenu CapitalBhagwati RealityDue Apr 2027, extended 4 mo—11%
Katware Business SquareKatware Builders & DevelopersDue Oct 2027, extended 4 mo——
Morya ParkAshok Chunilal SamsukhaDue Nov 2028—10%
Namavira ApartmentAastha DevelopersDue Dec 2026——
NavyashodaVijay Kamble Developers8 mo late—11%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology