7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Sai AanandAshwini BuildconDue Apr 2029, extended 4 mo——
Shilpa MillenniumShilpa EstateDue Jan 2027, extended 4 mo——
Shree ParshwanathDarshan Anil LodhaDue Apr 2028, extended 4 mo——
The Platinum Mall By ParksydeJaikumar Constructions LtdDue Sep 2028, extended 4 mo——
Vinayaka NamanSaptashrungi Builders & Associates11 mo late——
Krishnam NiwasS S DevelopersCompleted—67%
Reliable Commercial ComplexShree Balaji DevelopersCompleted, extended 1 yr——
Samarth ResidencyAnil Haribhau Pingale1 yr 10 mo late——
Shree Siddhivinayak HeightsShree Vastu DevelopersCompleted—42%
AbhinavA C Jain Builders And Developers LLPCompleted—8%
Atharva ParkDhanesh Narayan SarodeCompleted——
Gajanan Park phase 3 - Building DJaiprasad constructions and developers LLPCompleted——
Highland SkyAli Janamuddin SiddiquiDue Nov 2026, extended 4 mo—22%
Kamlaba Business AvenueKashibas InfratechCompleted—35%
NestKushavart RealtorsDue Nov 2026, extended 4 mo—15%
Ramalya HarmonyKaustubh Rajendra PingaleCompleted—10%
Shree Tirumala Magnus ApartmentRoongta Homes LLPCompleted—29%
The Landmark ApartmentAd EnterprisesCompleted—29%
Aanandam CitySwapnil Anil MogalDue Apr 2027, extended 4 mo——
Northside ApartmentShreevishwa BuildconCompleted—17%
Shashi Siddhi AnnexeSiddhivinayak AssociatesDue Apr 2029, extended 4 mo—8%
Shivram Residency 2Maheshwar EnterprisesCompleted—68%
Ananta Row BungalowsKetan Santu ChakaneCompleted—36%
Babubhais KrishnakunjVinod Dilipkumar MajithiaDue Apr 2027, extended 4 mo——
Comfort ZoneBhoomi DevelopersCompleted—10%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology