Completion was pushed back 4 months, to Dec 2028; no MahaRERA orders on record; 0% of its units are booked.

Chehedi Bk, Nashik 422214 · by Vishal Krishnadeo Desale

DeliveryExtended 4 moPromised Aug 2028 · now due Dec 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 71 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Dec 2028

  • This projectRegistered 23 Oct 2023, completion promised 31 Aug 2028, revised to 31 Dec 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600053283
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160005328323 Oct 202331 Aug 202831 Dec 2028Vishal Krishnadeo DesaleProject page
Documents53

2 documents held by Deedo, 51 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN Card.pdf · uploaded 6 Sep 2023Source

Legal

  • Legal Title reportTitle Report - The Rising Desale Patil Developers.pdf · uploaded 24 Aug 2023Source
  • Declaration Form BFORM B.PDF · uploaded 24 Aug 2023Source

Migrated

  • 1 Copy of the legal title reportTitle Report - The Rising Desale Patil Developers.pdf · uploaded 24 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)Govt Mojni Land.pdf · uploaded 24 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan.pdf · uploaded 24 Aug 2023Source
Show all 53 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentthe rising commencement.pdf · uploaded 24 Aug 2023Source
  • 1 Declaration in FORM BFORM B.PDF · uploaded 24 Aug 2023Source
  • 1 CERSAI detailsDECLARATION CERSAI.PDF · uploaded 24 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A.PDF · uploaded 24 Aug 2023Source
  • 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 24 Aug 2023Source
  • 1 Proforma of Allotment letterPERFORMA OF ALLOTMENT.pdf · uploaded 24 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDECLARATION OF DEVIATION IN ALLOTMENT.PDF · uploaded 24 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDECLAR OF DEVIATION IN AGREE SAL.PDF · uploaded 24 Aug 2023Source
  • 1 PAN CardPAN Card.pdf · uploaded 6 Sep 2023Source
  • 1 a Details of encumbrances concerned to FinanceDECLARATION LEGAL.pdf · uploaded 6 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceFinancial Encumbrance.pdf · uploaded 6 Sep 2023Source
  • 1 b Details of encumbrances concerned to LegalDECLARATION LEGAL.pdf · uploaded 6 Sep 2023Source
  • 2 b Details of encumbrances concerned to LegalFinancial Encumbrance.pdf · uploaded 6 Sep 2023Source
  • 1 Declaration about Commencement CertificateScan20230906160336.pdf · uploaded 6 Sep 2023Source
  • 1 Other – TechnicalNMC MAIL.pdf · uploaded 25 Sep 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)new form 3_merged.pdf · uploaded 14 Oct 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A REAL ESTATE PROJECTS.PDF · uploaded 14 Oct 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Apr 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 23 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 23 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPLOAD - FORM 3 - APRIL TO JUNE.pdf · uploaded 12 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPLOAD - FORM 3 - JULY TO SEPT.pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - DEC 2024.pdf · uploaded 10 Mar 2025Source
  • Form 1FORM 1 2024-25 Q4.pdf · uploaded 17 Apr 2026Source
  • Form 2FORM 2 2024-25 Q4.pdf · uploaded 17 Apr 2026Source
  • Form 3FORM 3 2024-25 Q4.pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE 2024-25 Q4.pdf · uploaded 17 Apr 2026View
  • Form 1FORM 1 2025-26 Q1.pdf · uploaded 17 Apr 2026Source
  • Form 2FORM 2 2025-26 Q1.pdf · uploaded 17 Apr 2026Source
  • Form 3FORM 3 2025-26 Q1.pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE 2025-26 Q1.pdf · uploaded 17 Apr 2026View
  • Form 1FORM 1 2025-26 Q2.pdf · uploaded 17 Apr 2026Source
  • Form 2FORM 2 2025-26 Q2.pdf · uploaded 17 Apr 2026Source
  • Form 3FORM 3 2025-26 Q2.pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE 2025-26 Q2.pdf · uploaded 17 Apr 2026View
  • Form 1FORM 1 2025-26 Q3.pdf · uploaded 17 Apr 2026Source
  • Form 2FORM 2 2025-26 Q3.pdf · uploaded 17 Apr 2026Source
  • Form 3FORM 3 2025-26 Q3.pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE 2025-26 Q3.pdf · uploaded 17 Apr 2026View

Technical

  • Documentscan.pdf · uploaded 24 Aug 2023Source
  • DocumentGovt Mojni Land.pdf · uploaded 24 Aug 2023Source
  • Other – TechnicalNMC MAIL.pdf · uploaded 25 Sep 2023Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 23 Apr 2024Source
  • DocumentFORM 1 - DEC 2024.pdf · uploaded 10 Mar 2025Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 23 Apr 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 125/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Shop71 units in all
Address
Survey No 125/2, Deolali Chehadi Shiv Road, S No 125/2 ChehadiPIN 422214
Village
Chehedi Bk, Nashik taluka
Land area for this project
1,166 sq m (12,551 sq ft)
Permissible built-up area
4,973 sq m (53,526 sq ft)
Sanctioned built-up area
4,973 sq m (53,526 sq ft)
Designated bank account
154
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 125/2

Land as published on MahaRERA's project page

SURVEY NO 125/2

Boundaries

North
Plot
South
Plot
East
Building
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking71 units

0 of 71 units booked (0%), as the promoter reported to MahaRERA

2BHK · 60 unitsShop · 11 units
TypeCarpet areaUnitsBooked
2BHK54.86 sq m · 591 sq ft100
2BHK56.27 sq m · 606 sq ft100
2BHK57.98 sq m · 624 sq ft200
2BHK57.99 sq m · 624 sq ft200
Shop9.9 sq m · 107 sq ft10
Shop15.41 sq m · 166 sq ft70
Shop18.87 sq m · 203 sq ft10
Shop25.81 sq m · 278 sq ft10
Shop33.29 sq m · 358 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectTejas More—
Chartered accountantHimesh Patel—
EngineerAudumbar Wani—

Source: MahaRERA project page. Contact details are not shown.