7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Sukan FloraArvindbhai Bavchandbhai RakholiyaDue May 2029, extended 4 mo—15%
AdvaitAnanda DevelopersDue Apr 2029, extended 4 mo—4%
Comrade Prabhatkar Co-Operative Hsg SocietyVastu Builders And Land DevelopersDue Feb 2029—69%
SaisquareVijay Vasudev Lalwani10 mo late——
Vedant AanandvanGorakshnath Dashrath MhaskeDue Apr 2030, extended 4 mo——
Aaradhy Classic Building No.2Siddhi CorporationDue Feb 2029, extended 4 mo—22%
Al Safa HeightsMuzammil Faridoddin KhatibDue Dec 2026, extended 4 mo—30%
Bhagyavanti Co-operative Housing Society LimitedHardik DevelopersDue Apr 2027, extended 4 mo—68%
Morya PrideMorya Buildrs And DevelopersCompleted——
Symphony Co-Op Housing SocietyJ B ConstructionCompleted—2%
Qasrul Khulafa 3Makani BuildconDue Apr 2028, extended 4 mo——
Suhas RegencyBhagurkar DevelopersCompleted——
Brahmgiri ParkShreevastu BuildconDue Apr 2029, extended 4 mo—67%
Primrose ResidencyBhumit Real Estate Private LimitedDue Apr 2028, extended 4 mo—9%
Surya HeightsBhavani ConstructionsDue Apr 2029, extended 4 mo—2%
Ekdant HeightsGovinda ConstructionCompleted—12%
Raunakk HeightsKmr Builders & AssociatesDue Apr 2029, extended 4 mo—10%
Shyam PalaceShreenathji DevelopersDue Apr 2028, extended 4 mo—3%
Tabeer VistaTabeer PropertiesCompleted—21%
Attal Highstreet Phase AAttal BuildersDue Oct 2033, extended 4 mo——
Daulat ApartmentSunita Sanjay PatilDue Jul 2028, extended 4 mo——
Shivsundar HeightsG.s.enterprisesDue Apr 2029—6%
Bajrang HeightsPrasad Constructions1 yr 11 mo late——
LatavishwaShree DevelopersDue Dec 2026——
Avadhoot High City Phase 1Avadhoot DevelopersDue Dec 2028——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology