Deedo IDDL-NSK-NASHIK7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
7 in 10 registrations run late here
4,253 MahaRERA registrations in Nashik and the places within it
376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nashik
4,202 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Unity HeightsNirmaan Engineers And Contractors | Completed | — | — |
| Sadguru HeightsSadguru Builders And Developers | Due Apr 2028, extended 4 mo | — | — |
| Sahaj ApartmentSankhla Buildcon | Due Mar 2027 | — | — |
| Feriha HeightsAroma Developers | Due Jul 2027, extended 4 mo | — | — |
| Maa Karni Krupa Surekha HeightsShree Radhey Group | Due Apr 2027, extended 4 mo | — | — |
| Racca LegacyPoonam Shrenik Surana | Due Apr 2027, extended 4 mo | — | 45% |
| Sarode ParkNarayan Labhu Sarode | Due Apr 2030, extended 4 mo | — | 1% |
| Shiv EmpireLandmark infra | Due Apr 2028, extended 4 mo | — | — |
| Tanishq Park RoyalsM S Builders & Developers | Due Apr 2027, extended 4 mo | — | 8% |
| IstanaWaterstone LLP | Due Apr 2028, extended 4 mo | — | 11% |
| Mangalmurti ParkSavita Mohan Sangle | Due Jul 2028, extended 4 mo | — | 31% |
| Samarth GauravGaurav Shrikant Sohani | Completed | — | 63% |
| SterlingArihant Construwell | Due Jan 2027, extended 4 mo | — | — |
| Vrindavan BlissVrindavan Contractors LLP | Due Jul 2028, extended 4 mo | — | — |
| Nirmiti GloryNirmiti Builders And Developers | Due Apr 2028, extended 4 mo | — | — |
| Shilp MeridianHemant Dattatraya Gaikwad | Due Jul 2028, extended 4 mo | — | — |
| Dindori Trade CenterShree Laxmi Balaji Buildcon | Due Apr 2028, extended 4 mo | — | — |
| Ajanta Nagari Co Op Hsg SocietyKhilendra Mohabiya | 3 mo late | — | — |
| Parameshwaram ResidencyVasudevay Builders & Developers | Due Apr 2029, extended 4 mo | — | — |
| Saidham AppartmentBsr Realty | Completed | — | 29% |
| Universal PrideUniversal Buildcon | Due Apr 2028, extended 4 mo | — | — |
| City Business Square ParkDream Builders And Developers | Due Apr 2027, extended 4 mo | — | — |
| Ekdant Row-HousesVinit Baburao Deore | Due Apr 2027, extended 4 mo | — | — |
| Hari Kunj Heights ApartmentGoodwill Realtors | Completed | — | — |
| Saptashrungi PoojaSaptashrungi Developers | Completed | — | 69% |
Localities in Nashik
- Nashik1,372 projects
- Nashik (M Corp.)1,251 projects
- Nashik301 projects
- Aanandwali94 projects
- Deolaligaon67 projects
- Nashik Road67 projects
- Satpur56 projects
- Jail Road55 projects
- Deolali (Cb)50 projects
- Makhmalabad45 projects
- Pathardi37 projects
- Adgaon30 projects
All 103 localities
- Nashik Shiwar29
- Sinnar(M Cl)29
- Igatpuri (M Cl)28
- Vihitgaon28
- Kamatwade25
- Mhasrul25
- Bhagur Rural24
- Indiranagar24
- Sansari24
- Pimpalgaon Baswant23
- Chehedi Bk22
- Ozar (Ct)22
- Chandshi21
- Sinnar21
- Sinnar16
- Malegaon (M Corp.)15
- Wadala Shivar15
- Igatpuri14
- Gangapur13
- Chunchale10
- Dasak10
- Dindori10
- Jalalpur9
- Shinde9
- Belatgavhan8
- Palse8
- Ambad Khurd7
- Kasbe Vani7
- Lasalgaon7
- Panchak7
- Pimprisado7
- Bhagur (M Cl)6
- Gondedumala6
- Govardhan5
- Niphad5
- Satana4
- Malegaon3
- Niphad3
- Saikheda3
- Shramik Nagar3
- Trimbakeshwar3
- Yeola3
- Chandvad (Ct)2
- Dindori2
- Ghoti Bk. (Ct)2
- Girnare2
- Kawanai2
- Manmad (M Cl)2
- Naigaon2
- Nilgavhan2
- Ozar Gaon2
- Sangameshwar (Ct)2
- Saradwadi2
- Shivaji Nagar2
- Soyagaon (Ct)2
- Trimbakeshwar2
- Agartakli1
- Ashok Nagar1
- Behed1
- Beladgavhan1
- Borivali1
- Deola1
- Deshwandi1
- Gaulane1
- Gitakunj1
- Jaulke(Dindori)1
- Kasbe Sukene1
- Khambale1
- Madsangvi1
- Maparwadi1
- More Nagar1
- Mungsara1
- Naikwadi1
- Nandadgaon1
- Nandgaon1
- Pakhal Road1
- Pardevi1
- Pimpalgaon Bahula1
- Pimpalgaon Garudeshwar1
- Pimpalgaon Ketaki1
- Pimpalgaon Najik (Ct)1
- Satpur Colony1
- Surgana1
- Talegaon1
- Talegaon(Dindori)1
- Titoli1
- Trimbak (M Cl)1
- Umarane1
- Vilholi1
- Vinchur1
- Wasali1
Other districts
Most active promoters
- Roongta Homes Llp26 projects
- Jay Developers13 projects
- Kbc Global Limited12 projects
- Sanklecha Construction Private Limited11 projects
- Shah Builders And Developers11 projects
- Nashik Housing And Area Development Board10 projects
- Shreeji Life Space10 projects
- Deepak Kalyanji Chande9 projects
- Govinda Construction9 projects
- Sun Infrastructures Pvt. Ltd9 projects
Nashik, in questions
How many projects in Nashik run late?
7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.
Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology