7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Laxminarayan HeavenSahajanand Builders And DevelopersDue Apr 2029, extended 4 mo—11%
Rass Residency - Building ARass DevelopersCompleted—27%
Imperial TowerBijasani BuildtechDue Apr 2029, extended 4 mo—8%
ShantiniketanGhansham Bhavarilal RawatDue Apr 2027, extended 4 mo—56%
Sohan ParkSiddharth Sohanlal BhandariDue Apr 2028, extended 4 mo—79%
Advait ApartmentML Infra Build LLPDue Dec 2026—31%
Shree Kartikeya Phase 2Nirmiti InfraDue Feb 2027, extended 4 mo——
Yash ParkBharti Shashikant TargeDue Dec 2026——
Madhav ParkKapse DevelopersDue Nov 2027, extended 4 mo——
Shree Ganesh ApartmentRoyal Constructions10 mo late——
Ashiyana LuxuriaBrijwasi InfratechCompleted—17%
ElysianRoongta Homes LLPDue Jul 2032, extended 4 mo——
Kalapurnam Park Phase 2Dinkar Murlidhar PaldeDue Sep 2028——
Mukund Co-Op Housing SocietySamrat BuildconDue Apr 2027, extended 4 mo—20%
Parksyde HouseJaikumar Constructions Ltd, Roopali Nx, Divyesh Sejpal & Urvee Sejpal7 mo late——
Raunak VivantaKgr DevelopersDue Mar 2029, extended 4 mo—7%
Saubhagya ResidencyAjinkya Pravin Munot1 yr 5 mo late——
Shree Kausalyeshwar ResidencySunita Rajendra BhavsarDue Apr 2027, extended 4 mo—14%
Shree Sadguru Krupa HeightsShree Sadguru Krupa ConstructionCompleted—16%
Vinayak ResidencyAkshat Developers and Construction CompanyCompleted—43%
Krushna Pride 3Namdeo Govind BorhadeDue Apr 2027, extended 4 mo——
Rudra Greenfield Row BungalowN M Pekhale Infra Private LimitedCompleted——
Shreenivasa ResidencyShreenivasa Residency JVCompleted—17%
Divyadarshan Co-operative Housing Society LtdSai Vaishnavi BuildconDue Oct 2027, extended 4 mo——
Lotus HeightsJay Ambe PropertiesDue Dec 2029——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology