7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Subhashree Co Op Hsg SocLaxmi BuildcraftsDue Jul 2027, extended 4 mo——
Aero CityAero City RealtorsDue Apr 2030, extended 4 mo——
MadhubanSomvijay DevelopersDue Apr 2027, extended 4 mo—29%
Manikkrupa Co-operative Housing Society Limited NashikSiddhaganesh Builders And DevelopersDue Apr 2028, extended 4 mo—50%
Shanti Kiran ApartmentSahyog Vastu UdyogDue Apr 2028, extended 4 mo—24%
Rajashree Pride ApartmentNew Rajashree PropertiesCompleted——
Shree Padmaraj ResidencyShreekar ConstructionDue Aug 2028, extended 4 mo——
Highway PlazaDiya Isabelle Trading Co LLPDue Apr 2028, extended 4 mo——
Nathvandan AppartmentEcostone Builders & Developers5 mo late—2%
Saarthak ShantivanSaarthak ConstructionsDue May 2027, extended 4 mo——
Shilpa SolitaireShilpa EstateDue Apr 2028, extended 4 mo——
Shree Laxmi ApartmentAlka Uttam ShindeDue Apr 2028, extended 4 mo—35%
Shree Sadguru Vinayak Commercial ComplexShri Sadguru AssociatesDue Mar 2028—10%
Vandana Gauri Co-operative Housing Society Ltd. NashikAmol Shashikant AhirraoDue Apr 2028, extended 4 mo—64%
Vidhata Apartment Co-Op Housing Society LtdPravin Vasantrao DaradeCompleted—3%
Vivanta SquareBirari InfraconDue May 2027—6%
Ashtavinayak HeightsAshtavinayak Builders And DevelopersCompleted—10%
Bel AirA C Jain Builders And Developers LLPDue Apr 2031, extended 4 mo——
Neelam SrushtiNeelam Builders And DevelopersDue Apr 2028, extended 4 mo—37%
Sakar ImperiaDhwani DevelopersDue Apr 2029, extended 4 mo——
Sangamnere ComplexVishal Builders And DevelopersDue Apr 2029, extended 4 mo——
Saptashrungi HeightsShree Saptashrungi ConstructionsDue Jul 2027, extended 4 mo—22%
Shri Balaji HeightsShri Balaji DevelopersDue Nov 2027, extended 4 mo——
Orchid ResidencyMahesh Nanikram ChawalaCompleted——
Rhythm ApartmentShriniwasa DevelopersDue Dec 2028——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology