7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vastu TowerApurva Builders & DevelopersDue Apr 2027, extended 4 mo——
Amar Bhupali Co-Operative Housing Society Ltd. NashikAnand Builders And DevelopersCompleted—57%
Anuveena HeightsVivek Deepak MouleDue Jun 2027——
Ekdant EnclaveVSK DevelopersDue Apr 2028, extended 4 mo——
Labh GalaxyLabh InfraDue Jul 2029, extended 4 mo——
Sai Kuber ProjectSai Kuber Builders And DevelopersDue Apr 2027, extended 4 mo——
Bait E MuhammadOnyx ConstructionsDue Dec 2031—1%
Shivshambho Heights Co op Hsg Soc LtdYogesh Kailas HarakDue Aug 2027, extended 4 mo——
Shree Ganesh VistaSonali RealtyDue Apr 2028, extended 4 mo—2%
Amrut SwarSuprabhat BuildconDue Apr 2029, extended 4 mo——
Harshnil ResidencyOm Sai ConstructionDue Apr 2031, extended 4 mo——
Krishna EmeraldChaitanyaraj And Krishna Developers (Jv)Completed——
Rajbas PrideFourth Dimension PropertiesDue Jun 2027——
Happy Life At Apna GharShweta Infrastructure & Housing (I) Pvt. Ltd.Due Apr 2031, extended 4 mo——
Mauni AshishMalpani Kalya Construction LLPDue Apr 2030, extended 4 mo——
Shree Ganesh VyyomPrakash Raman ChaudhariDue Apr 2029, extended 4 mo——
Morya ParkRavindra Developers Private LimitedDue Mar 2028—26%
Krushna Pride 4Krushna PrideDue Apr 2029, extended 4 mo——
Three Leaves Phase ThreeDeepak Infra And Homes Private LimitedDue Dec 2030——
Lotus ParkShree Panchmukhi DevelopersDue Jul 2027, extended 4 mo——
Vrundavan VillaGhanshyambhai Gokalbhai ViramgamaCompleted——
Shiv Park ColonyShiw Shambho BuildconDue Apr 2027, extended 4 mo——
Shubh AarambhShubhshree InfratechCompleted—39%
Sky RudraSunrise InfraCompleted——
SnehankitAnil Shantaram AmrutkarCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology