Others · 1 building · 254 unitsRERA P51600077153

Shilpa Solitaire

Deedo IDDP-NSK-JD7Y

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 0% of its units are booked.

Chandshi, Nashik 422003 · by Shilpa Estate · 33% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 254 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 23 Jul 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600077153
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160007715323 Jul 202431 Dec 202730 Apr 2028Shilpa EstateProject page
Documents98

1 document held by Deedo, 97 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan Card.pdf · uploaded 4 May 2024Source

Legal

  • Legal Title reportFinal Title Report.pdf · uploaded 4 May 2024Source
  • Declaration Form BForm B (2).pdf · uploaded 4 May 2024Source
  • Other – LegalAnnexture A.PDF · uploaded 23 May 2024Source
  • Other – LegalSale Deed - converted.pdf · uploaded 23 May 2024Source
  • Other – Legal7 12.pdf · uploaded 3 Jun 2024Source
  • Other – LegalPartnership Deed and Retirement Deed Final.pdf · uploaded 13 Jun 2024Source
Show all 98 documentsShow fewer documents

Legal

  • Other – LegalClarification Letter Final.pdf · uploaded 13 Jun 2024Source
  • Other – LegalMO U.pdf · uploaded 13 Jun 2024Source
  • Legal Title reportFlow of Title.pdf · uploaded 13 Jun 2024Source
  • Legal Title reportSearch Report.pdf · uploaded 13 Jun 2024Source

Migrated

  • 1 PAN CardFirm Pan Card.pdf · uploaded 4 May 2024Source
  • 1 Copy of the legal title reportFinal Title Report.pdf · uploaded 4 May 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrances concerned to Finance.PDF · uploaded 4 May 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrances concerned to Legal.PDF · uploaded 4 May 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances concerned to Finance.PDF · uploaded 4 May 2024Source
  • 2 b Details of encumbrances concerned to LegalEncumbrances concerned to Legal.PDF · uploaded 4 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan No - 1.pdf · uploaded 4 May 2024Source
  • 2 Copy of Layout Approval (in case of layout)Plan No -2.pdf · uploaded 4 May 2024Source
  • 3 Copy of Layout Approval (in case of layout)Plan No -3.pdf · uploaded 4 May 2024Source
  • 4 Copy of Layout Approval (in case of layout)Plan No - 4.pdf · uploaded 4 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan No - 1.pdf · uploaded 4 May 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan No -2.pdf · uploaded 4 May 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan No -3.pdf · uploaded 4 May 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan No - 4.pdf · uploaded 4 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommcencement Certificate 26-2-24.PDF · uploaded 4 May 2024Source
  • 1 Declaration in FORM BForm B (2).pdf · uploaded 4 May 2024Source
  • 1 CERSAI detailsCERSAI REPORT.PDF · uploaded 4 May 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsOther.pdf · uploaded 4 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Declaration about Separate Bank Account.PDF · uploaded 4 May 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviations of Allotment Letter.PDF · uploaded 4 May 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations - Solitaire_1 (2 files merged).pdf · uploaded 23 May 2024Source
  • 1 Proforma of Allotment letter1 Proforma of Allotment letter-pages-deleted.pdf · uploaded 23 May 2024Source
  • 1 Other – LegalAnnexture A.PDF · uploaded 23 May 2024Source
  • 2 Other – LegalSale Deed - converted.pdf · uploaded 23 May 2024Source
  • 1 Other – TechnicalAnnexture A.PDF · uploaded 23 May 2024Source
  • 3 Other – Legal7 12.pdf · uploaded 3 Jun 2024Source
  • 2 Copy of the legal title reportFlow of Title.pdf · uploaded 13 Jun 2024Source
  • 3 Copy of the legal title reportSearch Report.pdf · uploaded 13 Jun 2024Source
  • 4 Other – LegalClarification Letter Final.pdf · uploaded 13 Jun 2024Source
  • 5 Other – LegalMO U.pdf · uploaded 13 Jun 2024Source
  • 6 Other – LegalPartnership Deed and Retirement Deed Final.pdf · uploaded 13 Jun 2024Source
  • 1 Declaration about Commencement CertificateDeclaration Shilpa.PDF · uploaded 28 Jun 2024Source
  • 1 Proforma of Agreement for saleATS Shilpa Solitaire Corrected as per PNS 12-6-24 Final (2).pdf · uploaded 3 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT-AFS.pdf · uploaded 3 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Shilpa Solitaire-CA Cert_revised_Signed.pdf · uploaded 12 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Solitair SEPT 2024.pdf · uploaded 6 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Solitair DEC 2024.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SEPT 2024.pdf · uploaded 6 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 DEC 2024.pdf · uploaded 6 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 2024.pdf · uploaded 6 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 2024.pdf · uploaded 6 Feb 2025Source
  • Form 1Form 1 Solitair SEPT 2024.pdf · uploaded 12 Jul 2025Source
  • Form 2FORM 2 SEPT 2024.pdf · uploaded 12 Jul 2025Source
  • Disclosure of Sold and Booked InventoryS UNS 2024 25 COMPRESSED.pdf · uploaded 12 Jul 2025Source
  • Form 3FORM 3 SEPT 2024.pdf · uploaded 12 Jul 2025Source
  • Form 1Form 1 Solitair DEC 2024.pdf · uploaded 12 Jul 2025Source
  • Form 2FORM 2 DEC 2024.pdf · uploaded 12 Jul 2025Source
  • Form 3FORM 3 DEC 2024.pdf · uploaded 12 Jul 2025Source
  • Disclosure of Sold and Booked InventoryS UNS 2024 25 COMPRESSED.pdf · uploaded 12 Jul 2025Source
  • Form 1Form 1 Solitair MARCH 2025.pdf · uploaded 12 Jul 2025Source
  • Form 2FORM 2 MARCH 2025.pdf · uploaded 12 Jul 2025Source
  • Form 3FORM 3 MARCH 2025compressed.pdf · uploaded 12 Jul 2025Source
  • Disclosure of Sold and Booked InventoryS UNS 2024 25 COMPRESSED.pdf · uploaded 12 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Solitair SEPT 2024.pdf · uploaded 12 Jul 2025Source
  • Withdrawal Update Form 2FORM 2 MARCH 2025.pdf · uploaded 12 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 MARCH 2025compressed.pdf · uploaded 12 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Solitair JUNE 2025.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2FORM 2 JUNE 2025.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 JUNE 2025_compressed.pdf · uploaded 19 Jul 2025Source
  • Form 5 (FY 2024-2025)Shilpa Solitaire annual Report- FY 2024-25.pdf · uploaded 30 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Solitair JUNE 2025.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 2FORM 2 JUNE 2025.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 3FORM 3 JUNE 2025_compressed.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 1Form 1 Solitair.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 2FORM 2 SEPT 2025.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 3Shilpa Solitaire Sept 2025 Rera CA report_removed.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Solitair 05012026.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2Engineer Certificate-Chandashi 08012026.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 2025.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 1FORM 1 MARCH 2026.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2FORM 2 MARCH 2026.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3FORM 3 MARCH 2026.pdf · uploaded 15 May 2026Source
  • Form 5 (FY 2025-2026)FORM 5.pdf · uploaded 19 May 2026Source

Technical

  • DocumentPlan No - 1.pdf · uploaded 4 May 2024Source
  • DocumentPlan No -2.pdf · uploaded 4 May 2024Source
  • DocumentPlan No -3.pdf · uploaded 4 May 2024Source
  • DocumentPlan No - 4.pdf · uploaded 4 May 2024Source
  • DocumentPlan No - 1.pdf · uploaded 4 May 2024Source
  • DocumentPlan No -2.pdf · uploaded 4 May 2024Source
  • DocumentPlan No -3.pdf · uploaded 4 May 2024Source
  • DocumentPlan No - 4.pdf · uploaded 4 May 2024Source
  • Other – TechnicalAnnexture A.PDF · uploaded 23 May 2024Source

Technical (Architect)

  • DocumentForm 1 Solitair DEC 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentFORM 1 MARCH 2026.pdf · uploaded 15 May 2026Source

Technical (Engineer)

  • DocumentFORM 2 DEC 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentFORM 2 MARCH 2026.pdf · uploaded 15 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No. 28, S. No. 51/1(P)/51/2/51/3(P) at

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Conv Center Dinning, Conv Center Kitchen, Convention Center401, Guest Rooms, Shop254 units in all
Address
Plot No. 28, S. No. 51/1(P)/51/2/51/3(P) at Village Chandshi, Taluka Nashik, District Nashik 422003, Mouje Chandshi, Near Hotel Red RosePIN 422003
Village
Chandshi, Nashik taluka
Land area for this project
3,020 sq m (32,507 sq ft)
Permissible built-up area
7,610 sq m (81,908 sq ft)
Sanctioned built-up area
7,610 sq m (81,908 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 28S. No. 51/1(P)/51/2/51/3(P) at

Land as published on MahaRERA's project page

Plot No. 28, S. No. 51/1(P)/51/2/51/3(P) at Village Chandshi, Taluka Nashik, District Nashik 422003

Boundaries

North
9 Meter Road
South
S No 52 and Plot No 27 of Sr No 51
East
Open Space
West
15 Meter Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking254 units

0 of 254 units booked (0%), as the promoter reported to MahaRERA

Conv Center Dinning · 2 unitsConv Center Kitchen · 1 unitConvention Center401 · 1 unitGuest Rooms · 14 unitsShop · 236 units
TypeCarpet areaUnitsBooked
Conv Center Dinning19.13 sq m · 206 sq ft10
Conv Center Dinning239.23 sq m · 2,575 sq ft10
Conv Center Kitchen106.27 sq m · 1,144 sq ft10
Convention Center401590.19 sq m · 6,353 sq ft10
Guest Rooms20.27 sq m · 218 sq ft10
Guest Rooms20.44 sq m · 220 sq ft20
Guest Rooms20.85 sq m · 224 sq ft10
Guest Rooms22.23 sq m · 239 sq ft60
Show all 29 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Guest Rooms23.34 sq m · 251 sq ft10
Guest Rooms26.43 sq m · 284 sq ft20
Guest Rooms36.28 sq m · 391 sq ft10
Shop8.6 sq m · 93 sq ft40
Shop8.75 sq m · 94 sq ft120
Shop8.93 sq m · 96 sq ft80
Shop10.45 sq m · 112 sq ft300
Shop11.59 sq m · 125 sq ft330
Shop11.8 sq m · 127 sq ft10
Shop11.83 sq m · 127 sq ft100
Shop12.64 sq m · 136 sq ft80
Shop13.12 sq m · 141 sq ft110
Shop13.39 sq m · 144 sq ft400
Shop14.82 sq m · 160 sq ft60
Shop14.85 sq m · 160 sq ft440
Shop16.77 sq m · 181 sq ft20
Shop16.87 sq m · 182 sq ft30
Shop18.99 sq m · 204 sq ft80
Shop27.17 sq m · 292 sq ft60
Shop30.75 sq m · 331 sq ft20
Shop34.82 sq m · 375 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Pankaj Jadhav—
Chartered accountantBhalgat Bothra & Associates Ca Tushar Lokhande—
Chartered accountantCa Prasad Yeola—
EngineerEr Mahendra Ukha Patil—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Chandshi

All 21 projects in Chandshi · Compare Shilpa Solitaire with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology