7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Tirupati Garden Phase IIIRiddhi Siddhi ConstructionsCompleted——
TulsiheightsJay VelopersCompleted, extended 1 yr 10 mo——
Utkarsh PalaceUtkarsh Builders And DevelopersCompleted, extended 2 yrs 4 mo—96%
Vande ResidencyVande DevelopersCompleted—39%
Vijay SnehJaydevelopersCompleted, extended 5 yrs 7 mo——
Vrindavan HeightShivsai BuildconCompleted——
WaterwaysSanklecha Construction Private LimitedDue Dec 2028——
Yashoda DazzlerAnubhooti Infrastructures Pvt Ltd6 yrs 4 mo late——
Akshar DeepAkshar EnterprisesCompleted——
Govind PlazaGovind Bhausaheb MadhwaiCompleted——
Icon EstateIcon Construction6 yrs 5 mo late—8%
Jajoo Naiks Amar Vrindavan ApartmentAmar Buildtech Pvt LtdCompleted——
Kalpraj ApartmentAkar DevelopersCompleted——
Laxmi ChayyaLaxmikripa DevelopersCompleted, extended 1 yr 6 mo——
Mahadev CornerMahadev ConstructionCompleted—53%
Malpani Saffron Building No 2Giriraj EnterprisesCompleted——
Motkaris GravityMotkari Constructions Private LimitedCompleted—36%
Nirmiti LifespaceNirmiti LifestyleCompleted—31%
Omkar Heights Co-Op Housing Society LtdOmkar Heights Co-Op Housing Society Ltd.Completed—50%
Parvati HeightsLaxminarayan ConstructionsCompleted—87%
Prayag GreensPrayag DeveloperCompleted——
RoyaleAshoka Infraways LimitedCompleted, extended 3 yrs——
SaiserenityJayinfrastreucturiesCompleted—100%
SaishrushtiJay DevelopersDue Feb 2028, extended 4 mo—76%
Samarth BlossomD G GroupCompleted—83%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology