Royale

Completion date passed

Nashik 422006 |Promoter: Ashoka Infraways Limited

18 Aug 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2018Promised completionLatest across registrations
30 Dec 2021Revised completion2 of 2 registrations pushed back, by up to 3 years
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.97730, 73.79838
Royale is at latitude 19.97730, longitude 73.79838.

Also registered as

Royale B C D
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years

P51600008360

The latest completion date on record passed 4 years and 10 months ago.

Registered
18 Aug 2017
Promised
31 Dec 2018
Revised
30 Dec 2021

Completion pushed back 6 months

P51600011935

The latest completion date on record passed 8 years and 4 months ago.

Registered
1 Sep 2017
Promised
31 Dec 2017
Revised
30 Jun 2018

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160000836018 Aug 201731 Dec 201830 Dec 2021Ashoka Infraways LimitedProject page
P516000119351 Sep 201731 Dec 201730 Jun 2018Ashoka Infraways LimitedProject page

Documents

4 documents held by Deedo

Registration certificates

  • Registration certificateP51600008360 · 18 Aug 2017ViewSource
  • Registration certificateP51600011935 · 1 Sep 2017ViewSource

Extension certificates

  • Extension certificateP51600011935 · 15 Jan 2018ViewSource
  • Extension certificateP51600008360 · 9 Sep 2021ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik

Survey, CTS, gat or plot numbers

12/1/1/2 P to 12/1/1/9 P

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology