Ashoka Infraways Limited
Company or firm · 5 projects · 7 MahaRERA registrations
Projects57 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date71%5 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| RoyaleP51600008360 | Nashik | 2017 | Not reported | 31 Dec 2018 | 30 Dec 2021 | +36 months |
| RoyaleP51600011935 | Nashik | 2017 | Not reported | 31 Dec 2017 | 30 Jun 2018 | +6 months |
| Kalpataru Ph-1P51600014684 | Nashik (M Corp.) | 2017 | Not reported | 30 Dec 2021 | — | On date |
| KalpataruP51600018371 | Nashik (M Corp.) | 2018 | Not reported | 30 Dec 2021 | — | On date |
| KalpataruP51600025437 | Nashik (M Corp.) | 2020 | Not reported | 30 Jun 2023 | — | On date |
| Kalpataru Phase-4P51600028206 | Nashik (M Corp.) | 2021 | Not reported | 30 Jun 2023 | — | On date |
| Kalpataru - Phase - 5P51600048136 | Nashik (M Corp.) | 2022 | Not reported | 30 Jun 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 36 months, for Royale (P51600008360).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology