Ashoka Infraways Limited

Company or firm · 5 projects · 7 MahaRERA registrations

Projects57 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date71%5 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
RoyaleP51600008360Nashik2017Not reported31 Dec 201830 Dec 2021+36 months
RoyaleP51600011935Nashik2017Not reported31 Dec 201730 Jun 2018+6 months
Kalpataru Ph-1P51600014684Nashik (M Corp.)2017Not reported30 Dec 2021—On date
KalpataruP51600018371Nashik (M Corp.)2018Not reported30 Dec 2021—On date
KalpataruP51600025437Nashik (M Corp.)2020Not reported30 Jun 2023—On date
Kalpataru Phase-4P51600028206Nashik (M Corp.)2021Not reported30 Jun 2023—On date
Kalpataru - Phase - 5P51600048136Nashik (M Corp.)2022Not reported30 Jun 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Royale+36 mo
  • Royale+6 mo
  • Kalpataru Ph-1On date
  • KalpataruOn date
  • KalpataruOn date
  • Kalpataru Phase-4On date
  • Kalpataru - Phase - 5On date

Track record notes

  • 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Royale (P51600008360).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology