7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Kamal AvenueSai Samarth Construction2 yrs 3 mo late—100%
Kesar KalashKesar Infraspaces LLPCompleted—90%
Laxmi Meet ApartmentLaxmi Raaj ContructionCompleted——
Neelam Kalpataru ApartmentSwapnil Chandrakant TejaleCompleted—36%
Shram SafalyaJs GroupCompleted——
Siddhivinayak Trade CenterDhatrak ConstructionsDue Jul 2027, extended 4 mo——
The Landmark at XLO PointParadise Life SpacesDue Apr 2027, extended 4 mo——
Nilkanth DhamNilkanth InfraCompleted—62%
Prabhat Empire ApartmentPrabhat DevelopersCompleted—94%
Prathmesh ParadiseRavikant Vishwanath Ghuge4 yrs 8 mo late—100%
Shree Hari EnclaveKukreja And Shah BuildconCompleted—58%
Akash LifestyleDeep Construction Builders & DevelopersCompleted—54%
Bolkar MajesticGanesh Tukaram BolkarDue Apr 2027, extended 4 mo—4%
Camp CentralPradnya Buildcon5 mo late——
Matoshri TowerShri Builders And Developers3 yrs 3 mo late—65%
Nalini Vijay ApartmentMatoshri BuildconCompleted—73%
Prabhu Business CenterPacific BuildersCompleted—37%
Shubham Shopping CenterShree Ganesh Builders And Developers2 yrs 11 mo late——
Vrundavan ApartmentShree AssociatesCompleted—45%
67 GreensGreenlife Developers1 yr 11 mo late—37%
Flora AvenueUnity DevelopersDue Mar 2027—12%
Gajra NandanvanGajra AssociatesCompleted——
Jolly Luxuria ApartmentGayatri DevelopersCompleted—75%
Madhav HeightsKapse DevelopersCompleted——
Nandanvan ResidencySushil Developers3 yrs 4 mo late—75%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology