Matoshri Tower
Deedo IDDP-NSK-MQ13Its promised completion date, Aug 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 65% of its units are booked.
Indiranagar, Nashik 422009 · by Shri Builders And Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Aug 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 13 Sep 2021, completion promised 31 Aug 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600030754
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600030754 | 13 Sep 2021 | 31 Aug 2023 | 31 Aug 2023 | Shri Builders And Developers | Project page |
Documents31
2 documents held by Deedo, 29 filings listed on MahaRERA's project page
Show all 31 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportTITLE REPORT.pdf · uploaded 25 Aug 2021Source
- 1 Details of encumbrancesDECLARATION ENCUMBERANCE.pdf · uploaded 25 Aug 2021Source
- 1 Copy of Layout Approval (in case of layout)LAND LAYOUT.pdf · uploaded 25 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN.pdf · uploaded 25 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 25 Aug 2021Source
- 1 Declaration about Commencement CertificateFORMAT D.pdf · uploaded 25 Aug 2021Source
- 1 Declaration in FORM BFORM B-BUILDER.pdf · uploaded 25 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 25 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryANNEXURE A.pdf · uploaded 25 Aug 2021View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA CERTIFICATE.pdf · uploaded 25 Aug 2021Source
- 1 Proforma of Allotment letterAGREEMENT FORMAT.pdf · uploaded 25 Aug 2021Source
- 2 Proforma of Allotment letterALLOTMENT LETTER FORMAT.pdf · uploaded 25 Aug 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 2 Mar 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed (1).pdf · uploaded 2 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 2 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceLegal Encumbarance.pdf · uploaded 4 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalLegal Encumbarance.pdf · uploaded 4 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of Sep Bank ac.pdf · uploaded 4 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure-Santosh.pdf · uploaded 6 Mar 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure-Atul.pdf · uploaded 6 Mar 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure-Yasin.pdf · uploaded 6 Mar 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 873/1 2/58 PLOT NO 56
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK20 units in all
- Address
- S No 873/1 2/58 Plot No 56, Indiranagar, IndiranagarPIN 422009
- Village
- Nashik (M Corp.), Nashik taluka
- Land area for this project
- 493 sq m (5,307 sq ft)
- Permissible built-up area
- 1,544 sq m (16,623 sq ft)
- Sanctioned built-up area
- 1,544 sq m (16,623 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 873/1 2/58 PLOT NO 56
Boundaries
- North
- Plot No 54
- South
- 9 Meter Colony Road
- East
- Colony Road
- West
- Plot No 55
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
13 of 20 units booked (65%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 50.51 sq m · 544 sq ft | 5 | 2 |
| 2BHK | 51.16 sq m · 551 sq ft | 5 | 3 |
| 2BHK | 53.53 sq m · 576 sq ft | 5 | 3 |
| 2BHK | 60.33 sq m · 649 sq ft | 5 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ram Anerao | — |
| Chartered accountant | Amit Banchhode | — |
| Engineer | Ram Anerao | — |
Source: MahaRERA project page. Contact details are not shown.