7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Ved SanskrutiKalki Developers11 mo late—2%
Iqra HeightsSoni BuildconCompleted——
Shivshakti LuxuriaHina Sanjay PatelCompleted——
Yashoda PrimeAnubhooti Infrastructures Pvt Ltd8 mo late—10%
Anand Sarita Co. Op. Hsg. Soc. Ltd.Siddhivinayak DevelopersCompleted——
Greenview Cooperative Housing Society LimitedGreenview Cooperative Hossing Society Private Limited1 yr 7 mo late——
Nanekar HeightsKalki DevelopersDue Apr 2028, extended 4 mo——
Nine Square HeightsEkdant Builders And DevelopersCompleted——
Sanket LuxuriaShree Sanket DevelopersCompleted—16%
The SolitaireSupreme Fortune Developers LLPDue Apr 2028, extended 4 mo—14%
Vaishnavi ResidencyVaishnavi EnterprisesCompleted—38%
Rajashree ChintanRajashree PropertiesCompleted—20%
Sai Datta Tower BAPURVA BUILDERS and DEVELOPERSDue Feb 2027, extended 4 mo——
Vraj ArcadeVraj ConstructionCompleted—78%
Yashleela ResidencyShiv BuildconCompleted—64%
Avani Co-Operative Housing Society LtdAvani Co-Operative Housing Society LtdCompleted——
Balaji HeightsBalaji DevelopersDue Dec 2026——
Bhandari Greens Phase 3Ujjawala Sohanlal BhandariCompleted—62%
Empyrean HomesAjinkya Vilas PhadDue Mar 2028——
Shivalik SkyraaYogeshwar InfratechDue Apr 2029, extended 4 mo——
Tirupati ParkSnehananad ConstructionCompleted—63%
Welcome Co-Operative Housing Society Ltd.Weclome Co-Operative Housing Society LtdCompleted——
Arunodaya Co Operative Housing Society Limited Nashik RoadArunodaya Co-Operative Housing Society Limited Nashik Road11 mo late—88%
Atharva Heights ApartmentAvinash Shamrao PatilCompleted——
Bhavik Apartment Co. Op. Hsg. SocietyHiray and Jagtap AssociatesCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology