Nanekar Heights

Certificate Signed

Deolali (Cb), Nashik 422101 |Promoter: Kalki Developers

Residential / Group HousingRERAP51600048259
22 Dec 2022Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
23Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, 3BHK23 units in all
Address
S. No. / G. No. 58/4B/3/2/2 of Deolali Shiwar, Nashik, Jai Bhavani Road, Artillery Near Nanekar Mala, DeolaliPIN 422101
Designated bank account
229
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.94538, 73.82694
Nanekar Heights is at latitude 19.94538, longitude 73.82694.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
22 Dec 2022
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160004825922 Dec 202231 Dec 202730 Apr 2028Kalki DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Nanekar Heights423

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 23 units booked (0%), as the promoter reported to MahaRERA

1BHK · 2 units2BHK · 19 units3BHK · 2 units
TypeCarpet areaUnitsBooked
1BHK49.82 sq m · 536 sq ft10
1BHK55.5 sq m · 597 sq ft10
2BHK43.75 sq m · 471 sq ft30
2BHK62.19 sq m · 669 sq ft30
2BHK64.2 sq m · 691 sq ft30
2BHK64.73 sq m · 697 sq ft30
2BHK67.59 sq m · 728 sq ft30
2BHK68.84 sq m · 741 sq ft40
3BHK77.6 sq m · 835 sq ft10
3BHK89.6 sq m · 964 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 103 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan Card.pdf · uploaded 22 Nov 2022Source

Legal

  • Legal Title reportTitle Report-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • Declaration Form BForm B Developer (1).pdf · uploaded 22 Nov 2022Source

Migrated

  • 1 PAN CardFirm Pan Card.pdf · uploaded 22 Nov 2022Source
  • 1 Copy of the legal title reportTitle Report-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
Show all 104 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)Building Plan-Tanaji Raghunath Nanekar-2 (1).pdf · uploaded 22 Nov 2022Source
  • 2 Copy of Layout Approval (in case of layout)Building Plan-Tanaji Raghunath Nanekar (1).pdf · uploaded 22 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan-Tanaji Raghunath Nanekar-2 (1).pdf · uploaded 22 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan-Tanaji Raghunath Nanekar (1).pdf · uploaded 22 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate-Tanaji Raghunath Nanekar.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration in FORM BForm B Developer (1).pdf · uploaded 22 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 1 Proforma of Agreement for saleModel Agreement For Sale.pdf · uploaded 22 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account Declaration-Nanekar Heights.pdf · uploaded 22 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviations of the allotment letter.pdf · uploaded 22 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviations of AFS.pdf · uploaded 22 Nov 2022Source
  • 1 CERSAI detailsCERSAI Search Report.pdf · uploaded 10 Dec 2022Source
  • 1 Proforma of Allotment letterAllotment Lettr.pdf · uploaded 10 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit Report 2022-23 Signed Copy.pdf · uploaded 7 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Dec 2022.pdf · uploaded 11 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate March 2023.pdf · uploaded 11 May 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Dec 2022 Final.pdf · uploaded 11 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate March 2023 Final.pdf · uploaded 11 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Dec 2022.pdf · uploaded 11 May 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate March 2023.pdf · uploaded 11 May 2024Source
  • 1 Disclosure of sold/ booked inventoryQ3 -22 - Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 2 Disclosure of sold/ booked inventoryQ4 - 23 - Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 3 Disclosure of sold/ booked inventoryQ1 -23 -Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 4 Disclosure of sold/ booked inventoryQ2-23 - Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 5 Disclosure of sold/ booked inventoryQ3-23 - Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 6 Disclosure of sold/ booked inventoryQ4- 24 Nanekar heights.pdf · uploaded 8 Jul 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 AR Jun 23.pdf · uploaded 15 Jul 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 AR Sep 23.pdf · uploaded 15 Jul 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 AR Dec 23.pdf · uploaded 15 Jul 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 ER jun 23.pdf · uploaded 15 Jul 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 ER Sep 23.pdf · uploaded 15 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 ER Dec 23.pdf · uploaded 15 Jul 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 CA Cert Jun 23.pdf · uploaded 15 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 CA Cert Sep 23.pdf · uploaded 15 Jul 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 CA Cert Dec 23.pdf · uploaded 15 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Nanekar Form 2A Mar 24.pdf · uploaded 30 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR June 24.pdf · uploaded 1 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR Sep 24.pdf · uploaded 1 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR Dec 24.pdf · uploaded 1 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final CA june 24-min.pdf · uploaded 1 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final CA Sep 24-min.pdf · uploaded 1 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Fin CA Dec 24-min.pdf · uploaded 1 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER june 24.pdf · uploaded 1 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER -sep 24.pdf · uploaded 1 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER -Dec 24.pdf · uploaded 1 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure june 24.pdf · uploaded 1 Mar 2025Source
  • 2 Disclosure of sold/ booked inventoryDisclosure_ sep 24.pdf · uploaded 1 Mar 2025Source
  • 3 Disclosure of sold/ booked inventoryDisclosure Dec 24.pdf · uploaded 1 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final Anunal Report(Nanekar heights) - March- 24.pdf · uploaded 15 Mar 2025Source
  • Form 1Nnekar AR - March 24.pdf · uploaded 15 Oct 2025Source
  • Form 2Nnekar ER - March 24.pdf · uploaded 15 Oct 2025Source
  • Form 3Nnekar CA - March 24.pdf · uploaded 15 Oct 2025Source
  • Disclosure of Sold and Booked InventoryNanekar Disclosure Mar 24.pdf · uploaded 15 Oct 2025Source
  • Form 5 (FY 2024-2025)RERA audit report - 24 25 nanekar heights final.pdf · uploaded 20 Nov 2025Source
  • Form 1AR - Nanekar - March 25.pdf · uploaded 2 Dec 2025Source
  • Form 2ER - Nanekar - March 25.pdf · uploaded 2 Dec 2025Source
  • Form 3CA - Nanekar - March 25 final.pdf · uploaded 2 Dec 2025Source
  • Disclosure of Sold and Booked InventoryDis - Nanekar - March 25.pdf · uploaded 2 Dec 2025Source
  • Form 1AR - Nanekar - June 25.pdf · uploaded 2 Dec 2025Source
  • Form 2ER - Nanekar - June 25.pdf · uploaded 2 Dec 2025Source
  • Form 3CA - Nanekar - June 251 final.pdf · uploaded 2 Dec 2025Source
  • Disclosure of Sold and Booked InventoryDis - Nanekar - June 25.pdf · uploaded 2 Dec 2025Source
  • Form 1AR - Nanekar - Sep 25.pdf · uploaded 2 Dec 2025Source
  • Form 2ER - Nanekar - Sep 25.pdf · uploaded 2 Dec 2025Source
  • Form 3CA nanekar Sept 25 final.pdf · uploaded 2 Dec 2025Source
  • Disclosure of Sold and Booked InventoryDis - Nanekar - Sep 25.pdf · uploaded 2 Dec 2025Source
  • Form 5 (FY 2022-2023)RERA Audit Report 2022-23 Signed Copy.pdf · uploaded 8 Jan 2026Source
  • Form 5 (FY 2023-2024)Final Anunal Report(Nanekar heights) - March- 24.pdf · uploaded 8 Jan 2026Source
  • Withdrawal Update Form 1AR - Dec 25.pdf · uploaded 17 Jan 2026Source
  • Withdrawal Update Form 2ER - Dec 25.pdf · uploaded 17 Jan 2026Source
  • Withdrawal Update Form 3CA - Dec 25 final.pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2022-2023)Nanekar March 23.pdf · uploaded 2 Mar 2026Source
  • Form 2A (FY 2023-2024)Nanekar Form 2A - March 24.pdf · uploaded 2 Mar 2026Source
  • Form 2A (FY 2024-2025)Nanekar March 25.pdf · uploaded 2 Mar 2026Source
  • Withdrawal Update Form 1AR - Nanekar .pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 2ER - Nanekar .pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 3CA - Nanekar-Final.pdf · uploaded 18 Jun 2026Source
  • Form 5 (FY 2025-2026)RA -25-26-Final.pdf · uploaded 5 Sep 2026Source
  • Withdrawal Update Form 1AR - nanekar- June 26.pdf · uploaded 7 Oct 2026Source
  • Withdrawal Update Form 2ER - Nanekar - June 26.pdf · uploaded 7 Oct 2026Source
  • Withdrawal Update Form 3CA - nanekar- June 26-Final.pdf · uploaded 7 Oct 2026Source

Technical

  • DocumentBuilding Plan-Tanaji Raghunath Nanekar-2 (1).pdf · uploaded 22 Nov 2022Source
  • DocumentBuilding Plan-Tanaji Raghunath Nanekar (1).pdf · uploaded 22 Nov 2022Source
  • DocumentBuilding Plan-Tanaji Raghunath Nanekar-2 (1).pdf · uploaded 22 Nov 2022Source
  • DocumentBuilding Plan-Tanaji Raghunath Nanekar (1).pdf · uploaded 22 Nov 2022Source

Technical (Architect)

  • DocumentAR June 24.pdf · uploaded 1 Mar 2025Source
  • DocumentAR Sep 24.pdf · uploaded 1 Mar 2025Source
  • DocumentAR Dec 24.pdf · uploaded 1 Mar 2025Source
  • DocumentAR - nanekar- June 26.pdf · uploaded 7 Oct 2026Source

Technical (Engineer)

  • DocumentER june 24.pdf · uploaded 1 Mar 2025Source
  • DocumentER -sep 24.pdf · uploaded 1 Mar 2025Source
  • DocumentER -Dec 24.pdf · uploaded 1 Mar 2025Source
  • DocumentER - Nanekar - June 26.pdf · uploaded 7 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Deolali (CB), Nashik taluka

Survey, CTS, gat or plot numbers

S. No. / G. No. 58/4B/3/2/2 of Deolali Shiwar

Boundaries

North
58 Obli 4B Obli 3 Obli 2 P of Raghunath G Nanekar
South
Adj S No 58 Obli 4B Obli 3 Obli 3
East
18 meter DP Road
West
Adj S No 58 obli 4B Obli 3 Obli 2 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin R Bhattad—
Chartered accountantCA Pratik D Jai—
Chartered accountantParesh Sabadra—
EngineerChimanbhai D Patel—
EngineerFulchand Pal—
OtherFulchand Pal—
OtherRavindra Sukhdev Borse—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology