7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Aaradhya Garden ApartmentAbhirath Nimba Khairnar And Vimal Nimba Khairnar11 mo late——
K K Tower ApartmentShantai DevelopersDue Apr 2030, extended 4 mo——
Manik EnclaveNakshatra Builders and DevelopersDue Apr 2027, extended 4 mo——
Meenrung -Sky VillaRajendra Fakhruddin Motiwala8 mo late——
Purple Aashray ApartmentKiran Jayantibhai PatelCompleted——
Radhe Residency AppartmentJay Gurudev Enterprises11 mo late—70%
ShivdharaPragnesh Vajubhai Kathiriya And Kartik Sureshbhai DhananiCompleted——
Vrundavan ParkDhanesh Narayan SarodeCompleted——
Ashok ShreevastuJitu Ashok PawarCompleted—64%
Shivganga HillsMaheshwar EnterprisesCompleted—67%
Star AvenueNarkhede InfraCompleted—21%
Z SquareSmita Ashok ZopeDue Apr 2027, extended 4 mo—56%
Adhish AvenueShah EstatesCompleted——
Sai Chhaya ApartmentPm Builders And DevelopersCompleted—39%
Aarya AuspiciaAarya Builders11 mo late—63%
Aditya Residency ApartmentBhanudas Babulal MahajanCompleted——
Divine ResidencyAniket Anant PatilDue Apr 2027, extended 4 mo——
Latika HeightsShree Sai ConstructionsDue Apr 2027, extended 4 mo—32%
Mani VistaDharmishtha Manish NarodiaCompleted—38%
Shriram NiwasMorya Builders And DevelopersCompleted—38%
Amar SahajeevanAmar Buildtech Private LimitedDue Jan 2027, extended 4 mo—36%
Chaitanya VatikaRahul MarkandeDue Apr 2027, extended 4 mo——
Ambika VrundavanAmbika BuildconCompleted——
Ashapuri GirijaEkdant DevelopersCompleted—72%
Bhumi HeightsBhumi DevelopersCompleted—67%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology