7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shri Ganesh ApartmentAnil Hiralal Bhandari11 mo late——
Datta Prem ApartmentPremchand Nimbaji PatilCompleted—13%
Shiv Samarth ApartmentNitin Madhukar JagaleCompleted—83%
Shree Omkar AvenueShree Buildcon & AssociatesDue Dec 2027, extended 4 mo—11%
Shree Ram Krushna HeightsKisan Shivram BallalCompleted—17%
Trimurti AppartmentOm Shree ConstructionCompleted—68%
HarmonyShreya Bapurao SalunkeCompleted——
Kalpataru Baug - Phase 2Mr. Anil Ramkrishna Bhambere And Mrs. Vidya Anil BhambereDue Apr 2027, extended 4 mo—32%
Shree Gajanan ResidencyNew Shree Pawanputra DevelopersCompleted—63%
Shri Krishna TowerSarwdnya BuildconCompleted—58%
Shubharambh ApartmentGulab Prakash SonarCompleted—67%
TornaVastushilp RealtyCompleted—14%
Vaibhav Residency ApartmentVaibhav DevelopersDue Nov 2027, extended 4 mo——
Indraprastha AvenueRoyal BuildconCompleted——
Ojas ResidencyShree Gajanan Developers1 yr 3 mo late—20%
Shree Chaitanya ApartmentBhumi BuildconCompleted—21%
Shree Murlidhar Park Phase IRajendra Madhukar KaleDue Dec 2026—27%
Shyam IconicNeeta Mehulkumar Vaghela11 mo late—3%
Sukan GloryNaksh DevelopersCompleted—79%
Sulalit HeightsHarshal Hanmante Builders And Developers Private LimitedDue Apr 2027, extended 4 mo—36%
Swara III ApartmentD V Developers5 mo late——
Usha Co Operative Housing Society Limited, NashikAnand Builders And DevelopersCompleted—46%
Vedant Prestige ApartmentVedant ConstructionCompleted——
Tirumala EnclaveS P Builders10 mo late—20%
Vishwa Swarup HeightsVishwa ConstructionCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology