7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vrunda HeightsNishant DevelopersDue Mar 2031——
Kiran VertexSeva DevelopersDue Nov 2030, extended 4 mo——
AagamSbl HousingDue Jul 2032, extended 4 mo——
Nirmal ParkKulswamini BuildconDue Jul 2029, extended 4 mo——
Shreesafalya ApartmentShreeswami ConstructionsDue Jul 2032, extended 4 mo——
Ghule Sankul Phase-2Sudhir Subhash GhuleDue Apr 2031, extended 4 mo——
Swami Heights ApartmentMayur Sudhakar MahajanDue Jul 2031, extended 4 mo——
Swami SrushtiAkash Aniruddha GawadeDue Apr 2030, extended 4 mo——
Shilp SrushtiAdh DevelopersDue Apr 2029, extended 4 mo——
ABS Commercial ComplexAakruti Buildcon Private LimitedDue Oct 2027, extended 4 mo——
Shree Vastu HeightsSwastik DevelopersDue Apr 2032, extended 4 mo——
The PerennialTapan EstateDue Apr 2031, extended 4 mo——
Surabhi AltusVipam EnterprisesDue Jul 2031, extended 4 mo——
Namo Ganga ResidencyOm Shambhu DevelopersDue Apr 2032, extended 4 mo——
Sarkar Nanawali TowerSahil BuildconDue Apr 2030, extended 4 mo——
Western HillsRawat & Kakkar DevelopersDue Jul 2029, extended 4 mo——
Vallabh ApparmentDhananjay Nimba BoraseDue Jul 2029, extended 4 mo——
Surya HomesRamchandra Vitthal SuryawanshiDue Aug 2029, extended 4 mo——
Crystal Court Commercial ComplexShreekar ConstructionDue Oct 2028, extended 4 mo——
Janak ValenciaDk ConstructionDue Jul 2030, extended 4 mo——
Mid TownMap InfraDue Apr 2031, extended 4 mo——
Mysty HeavenVardan DeveloperDue Apr 2030, extended 4 mo——
Shivanjali AvenueMaheshwar EnterprisesDue Feb 2029, extended 4 mo——
Skyline AvenueSkyline InfraDue Aug 2030, extended 4 mo——
Swastik HeightsTuljaa RealtyDue Apr 2030, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology