3 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4,186in 103 localities
Registrations4,237some projects hold several
Completion still due1,3082,557 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

4,237 MahaRERA registrations in Nashik and the places within it

376 completed400 not yet due899 extended, not yet due2,190 past even the latest date372 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,186 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Nilkanth DeltaDharmesh Devjibhai SoliyaDue Dec 2029——
Moreshwar ParkNew Shreeram BuildersDue Aug 2029——
Anandam RowhomesShivay Buildecowell LLPDue Mar 2029——
Ganga Jamuna Heights ApptOmkar DevelopersDue Mar 2029——
Prabhat Laxmi ApartmentDayaben Bhagwanji Patel And Prabhat DevelopersDue Dec 2029——
Samruddhi SquareKrushnarpan BuildersDue Dec 2031——
Premsagar Co-Op Hsg SocietyAmit Shivaji BhandureDue Jan 2029——
Sai InfinityOm Sai DevelopersDue Jan 2031——
Pavan Putra Apartment Wing ATirupati BuildconDue Dec 2028——
Vrunda HeightsNishant DevelopersDue Mar 2031——
Kiran VertexSeva DevelopersDue Nov 2030, extended 4 mo——
AagamSbl HousingDue Jul 2032, extended 4 mo——
Nirmal ParkKulswamini BuildconDue Jul 2029, extended 4 mo——
Shreesafalya ApartmentShreeswami ConstructionsDue Jul 2032, extended 4 mo——
Ghule Sankul Phase-2Sudhir Subhash GhuleDue Apr 2031, extended 4 mo——
Swami Heights ApartmentMayur Sudhakar MahajanDue Jul 2031, extended 4 mo——
Swami SrushtiAkash Aniruddha GawadeDue Apr 2030, extended 4 mo——
Shilp SrushtiAdh DevelopersDue Apr 2029, extended 4 mo——
ABS Commercial ComplexAakruti Buildcon Private LimitedDue Oct 2027, extended 4 mo——
Shree Vastu HeightsSwastik DevelopersDue Apr 2032, extended 4 mo——
The PerennialTapan EstateDue Apr 2031, extended 4 mo——
Surabhi AltusVipam EnterprisesDue Jul 2031, extended 4 mo——
Namo Ganga ResidencyOm Shambhu DevelopersDue Apr 2032, extended 4 mo——
Sarkar Nanawali TowerSahil BuildconDue Apr 2030, extended 4 mo——
Western HillsRawat & Kakkar DevelopersDue Jul 2029, extended 4 mo——

Most active promoters

  1. Roongta Homes LLP26 projects
  2. Kbc Global Limited19 projects
  3. Jay Developers17 projects
  4. Nashik Housing and Area Development Board12 projects
  5. Sanklecha Construction Private Limited12 projects
  6. Om Developers11 projects
  7. Shah Builders And Developers11 projects
  8. Sun Infrastructures Pvt Ltd11 projects
  9. M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.10 projects
  10. Shreeji Life Space10 projects
Data through24 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology