3 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects4,186in 103 localities
Registrations4,237some projects hold several
Completion still due1,3082,557 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

4,237 MahaRERA registrations in Nashik and the places within it

376 completed400 not yet due899 extended, not yet due2,190 past even the latest date372 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,186 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Raj Apartment Co-Operative Housing Society Ltd - A WingShree Vayad EngineeringDue Dec 2030——
Amber Co. Op. Hsg. Soc.A R DevelopersDue Dec 2029——
Avadh ResidencyShiv RealtyDue Dec 2030——
Samarth DattakrupaPrime PropertiesDue Mar 2028——
Hanging EdenIshanya BuildconDue Mar 2032——
Saubhagya PrideArihant ConstructionsDue Mar 2030——
Shri Ram Residence ParkHp ConstructionDue Nov 2030——
Padmashree ParkPadma Omshree Builders Private LimitedDue Mar 2029——
Shiv Shakti ApartmentChaturbhai Dhirubhai KachaDue Sep 2028——
Vraj DarshanVSP InfrastructureDue Dec 2030——
Lotus TwinsLotus RealtyDue Mar 2029——
Shri Siddharth Co. Housing Soc. Ltd.A R DevelopersDue Dec 2029——
Ananta HeightsAnanta RealityDue Dec 2030——
Ishwar PremHarmony BuildconDue Jun 2029——
Rudra HeightsSakar BuildersDue Dec 2028——
Raghunadan HeightsPsbb ConstructionDue Jun 2029——
Silk RouteKalpataru HomesDue Dec 2030——
Shri Anant AvenueShri Anant Collab LLPDue Dec 2028——
Ayodhya ParkAyodhya InfraDue Mar 2029——
Baswant Trade CenterWayuDue Mar 2029——
Belmont By Milestone RealtyMilestone RealtyDue Jun 2031——
Wind ChimesPR EnterprisesDue Dec 2032——
Om Shivalay ResidencyArchana Nilesh ShimpiDue Dec 2031——
Jay Malhar ComplexAnuj InfraDue Mar 2029——
Sky NirvanaSunrise InfraDue Dec 2030——

Most active promoters

  1. Roongta Homes LLP26 projects
  2. Kbc Global Limited19 projects
  3. Jay Developers17 projects
  4. Nashik Housing and Area Development Board12 projects
  5. Sanklecha Construction Private Limited12 projects
  6. Om Developers11 projects
  7. Shah Builders And Developers11 projects
  8. Sun Infrastructures Pvt Ltd11 projects
  9. M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.10 projects
  10. Shreeji Life Space10 projects
Data through24 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology