7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Balaji PrestigeRahul Popatrao KakulteDue Dec 2026——
Sai Gaurav ResidencySai Balaji RealtorsDue Oct 2027, extended 4 mo——
Sai Park A B C D EVishal Suresh Vidhate5 mo late—8%
Siddhivinayak Town SquareSiddhivinayak DevelopersDue Apr 2028, extended 4 mo——
Durvankur ClassicGj Builders5 mo late——
Neo WorldNavkar DevelopersDue Apr 2031, extended 4 mo—14%
Pinak Co-op. Housing SocietyS R Developers11 mo late—59%
Icchamani HeightsIcchamani BuildconCompleted—50%
Lenkar S MajestiqKbsl PropertiesDue Apr 2029, extended 4 mo—1%
Prayag NakshatraPrayag RealtyDue Jul 2029, extended 4 mo——
Vishruth - AMangesh Ashok DhakraoDue Mar 2027, extended 4 mo—9%
Shrinivasa CastleJaywant Deoram AherDue Jun 2027, extended 2 yrs——
Pooja Akshata ApartmentNandan DevlopersCompleted——
RiverdaleArpanna Motors Private LimitedDue Apr 2028, extended 4 mo—20%
SolitaireInd DevelopersDue Apr 2029, extended 4 mo——
Kaushalyas Empress AvenueSai Group5 mo late—4%
Fateh LegacyOverseas Fateh Developers LLPDue Apr 2028, extended 4 mo——
Harshawardhan Building Number 1 Co Op Hsg Soc Limited NashikVipul Dilip GarjeDue Apr 2028, extended 4 mo—4%
Jaybhole Apartment Wing - BNirmiti GroupDue Jul 2027, extended 4 mo——
Nilanjan Vishwa ApartmentSanjay Madhavrao BhavsarDue May 2027, extended 4 mo—19%
Dev Darshan Heights ApartmentGoodwill PrideCompleted—34%
Raj Commercial CentreHarpalsingh Sohansingh Kohli8 mo late——
Sai Yamuna ParkSurya ConstructionDue Apr 2027, extended 4 mo—38%
THE AVENUE MILESTONE - TOWER 1 - Wing ANashik Construwell Private LimitedDue Apr 2028, extended 4 mo—6%
Time BlissSudeep Rajendra ChhajedCompleted—39%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology