Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Wadala Shivar, Nashik 422006 · by Ind Developers

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 84 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 1 Dec 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600053845
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000538451 Dec 202331 Dec 202830 Apr 2029Ind DevelopersProject page
Documents115

1 document held by Deedo, 114 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan Card.pdf · uploaded 27 Sep 2023Source

Legal

  • Other – LegalPartnership Deed.pdf · uploaded 27 Sep 2023Source
  • Legal Title reportTitle Report.pdf · uploaded 27 Sep 2023Source
  • Legal Title reportSALE DEED 15-1-10.pdf · uploaded 27 Sep 2023Source
  • Legal Title reportSALE DEED 15-11-20.pdf · uploaded 27 Sep 2023Source
  • Legal Title reportSALE DEED 15-21-30.pdf · uploaded 27 Sep 2023Source
  • Declaration Form BForm B_1 (3 files merged).pdf · uploaded 25 Oct 2023Source
Show all 115 documentsShow fewer documents

Migrated

  • 1 PAN CardFirm Pan Card.pdf · uploaded 27 Sep 2023Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 27 Sep 2023Source
  • 2 Copy of the legal title reportSALE DEED 15-1-10.pdf · uploaded 27 Sep 2023Source
  • 3 Copy of the legal title reportSALE DEED 15-11-20.pdf · uploaded 27 Sep 2023Source
  • 4 Copy of the legal title reportSALE DEED 15-21-30.pdf · uploaded 27 Sep 2023Source
  • 1 Copy of Layout Approval (in case of layout)Revised Plan 01.pdf · uploaded 27 Sep 2023Source
  • 2 Copy of Layout Approval (in case of layout)Revised Plan 02.pdf · uploaded 27 Sep 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentRevised Plan 01.pdf · uploaded 27 Sep 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentRevised Plan 02.pdf · uploaded 27 Sep 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificates.pdf · uploaded 27 Sep 2023Source
  • 1 CERSAI detailsCERSAI details.pdf · uploaded 27 Sep 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 27 Sep 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation of AL.pdf · uploaded 27 Sep 2023Source
  • 1 Other – LegalPartnership Deed.pdf · uploaded 27 Sep 2023Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal-Solitaire.pdf · uploaded 25 Oct 2023Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance-Solitaire.pdf · uploaded 25 Oct 2023Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal-Solitaire.pdf · uploaded 25 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance-Solitaire.pdf · uploaded 25 Oct 2023Source
  • 1 Declaration in FORM BForm B_1 (3 files merged).pdf · uploaded 25 Oct 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate-IND Dev-Initial.pdf · uploaded 25 Oct 2023Source
  • 1 Proforma of Allotment letterAllotment Letter-Solitaire.pdf · uploaded 25 Oct 2023Source
  • 1 Proforma of Agreement for saleAFS for Uploading.pdf · uploaded 26 Oct 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT.pdf · uploaded 26 Oct 2023Source
  • 1 Declaration about Commencement CertificateForm D-Solitaire.pdf · uploaded 22 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account Declaration-Solitaire.pdf · uploaded 22 Nov 2023Source
  • 1 Other – TechnicalCC.pdf · uploaded 22 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR - Dec 23.pdf · uploaded 25 Nov 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR - March 24.pdf · uploaded 25 Nov 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR- June 24.pdf · uploaded 25 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA - Dec 23.pdf · uploaded 25 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA -March 24.pdf · uploaded 25 Nov 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA - June 24.pdf · uploaded 25 Nov 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER June 24.pdf · uploaded 25 Nov 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER - March 24.pdf · uploaded 25 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)AR - Dec 23.pdf · uploaded 25 Nov 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure - Dec 23.pdf · uploaded 25 Nov 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure - March 24.pdf · uploaded 25 Nov 2024Source
  • 5 Disclosure of sold/ booked inventoryDisclosure - June 24.pdf · uploaded 25 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR -Sep 24.pdf · uploaded 4 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA -SEP 24.pdf · uploaded 4 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER Certificate sept 24.pdf · uploaded 4 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure - Sep 24 .pdf · uploaded 4 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 13 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)solitaire AR dec 24.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)solitaire CA dec 24.pdf · uploaded 20 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)solitaire eng dec 2024.pdf · uploaded 20 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)solitaire AR dec 24.pdf · uploaded 3 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)solitaire CA dec 24.pdf · uploaded 3 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)solitaire eng dec 2024.pdf · uploaded 3 Feb 2025Source
  • 2 Disclosure of sold/ booked inventorySolitire - dec 24.pdf · uploaded 10 Feb 2025Source
  • Form 1AR Cert.pdf · uploaded 27 Jun 2025Source
  • Form 2Form_2 Engineer.pdf · uploaded 27 Jun 2025Source
  • Form 3CA Solitire.pdf · uploaded 27 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure - March 25.pdf · uploaded 27 Jun 2025Source
  • Form 1Architect Certificate.pdf · uploaded 18 Aug 2025Source
  • Form 2Engineer Certificate.pdf · uploaded 18 Aug 2025Source
  • Form 3CA Certificate.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold booked inventory.pdf · uploaded 18 Aug 2025Source
  • Form 1AR - Sep 25.pdf · uploaded 17 Oct 2025Source
  • Form 2ER sept 25.pdf · uploaded 17 Oct 2025Source
  • Form 3CA Sept 25.pdf · uploaded 17 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure - Sept 25.pdf · uploaded 17 Oct 2025Source
  • Form 1AR- June 24.pdf · uploaded 29 Nov 2025Source
  • Form 1AR -Sep 24.pdf · uploaded 29 Nov 2025Source
  • Form 1solitaire AR dec 24.pdf · uploaded 29 Nov 2025Source
  • Form 2ER June 24.pdf · uploaded 29 Nov 2025Source
  • Form 2ER -Sep 24.pdf · uploaded 29 Nov 2025Source
  • Form 2solitaire eng dec 2024.pdf · uploaded 29 Nov 2025Source
  • Form 3CA - June 24.pdf · uploaded 29 Nov 2025Source
  • Form 3CA -SEP 24.pdf · uploaded 29 Nov 2025Source
  • Form 3solitaire CA dec 24.pdf · uploaded 29 Nov 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure - June 24.pdf · uploaded 29 Nov 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure - Sep 24 .pdf · uploaded 29 Nov 2025Source
  • Disclosure of Sold and Booked InventorySolitire - dec 24.pdf · uploaded 29 Nov 2025Source
  • Form 2A (FY 2024-2025)Form 2A March 25.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 1AR - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 1AR - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 2ER - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 2ER - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 3CA - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 3CA - Dec 25.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 1AR .pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 2ER.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 3CA Mar 26 _.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 1AR - June 26 .pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 2Latest - ER - June 26 .pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 3CA-Final.pdf · uploaded 1 Aug 2026Source

Technical

  • DocumentRevised Plan 01.pdf · uploaded 27 Sep 2023Source
  • DocumentRevised Plan 02.pdf · uploaded 27 Sep 2023Source
  • DocumentRevised Plan 01.pdf · uploaded 27 Sep 2023Source
  • DocumentRevised Plan 02.pdf · uploaded 27 Sep 2023Source
  • Other – TechnicalCC.pdf · uploaded 22 Nov 2023Source
  • DocumentSanction Plan-1-Solitaire.pdf · uploaded 22 Jun 2026Source
  • DocumentSanction Plan-2-Solitaire.pdf · uploaded 22 Jun 2026Source
  • OthersFormat D-Solitaire.pdf · uploaded 22 Jun 2026Source

Technical (Architect)

  • DocumentAR - Dec 23.pdf · uploaded 25 Nov 2024Source
  • DocumentAR - March 24.pdf · uploaded 25 Nov 2024Source
  • DocumentAR- June 24.pdf · uploaded 25 Nov 2024Source
  • Documentsolitaire AR dec 24.pdf · uploaded 20 Jan 2025Source
  • Documentsolitaire AR dec 24.pdf · uploaded 3 Feb 2025Source
  • DocumentAR - June 26 .pdf · uploaded 1 Aug 2026Source

Technical (Engineer)

  • DocumentAR - Dec 23.pdf · uploaded 25 Nov 2024Source
  • DocumentER - March 24.pdf · uploaded 25 Nov 2024Source
  • DocumentER June 24.pdf · uploaded 25 Nov 2024Source
  • Documentsolitaire eng dec 2024.pdf · uploaded 20 Jan 2025Source
  • Documentsolitaire eng dec 2024.pdf · uploaded 3 Feb 2025Source
  • DocumentLatest - ER - June 26 .pdf · uploaded 1 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel P. No. 1 at Wadala Shiwar, S. No. 15/6

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK84 units in all
Address
S. No. 15/6, P. No. 1 at Wadala Shiwar, Tal & Dist Nashik 422006, Ravi Shankar Marg, Behind Ayyapa MandirPIN 422006
Village
Wadala Shivar, Nashik taluka
Land area for this project
2,347 sq m (25,263 sq ft)
Permissible built-up area
7,274 sq m (78,297 sq ft)
Sanctioned built-up area
7,272 sq m (78,280 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

P. No. 1 at Wadala ShiwarS. No. 15/6

Land as published on MahaRERA's project page

S. No. 15/6, P. No. 1 at Wadala Shiwar, Tal & Dist Nashik 422006

Boundaries

North
9 Meter Colony Road
South
Area Out of Survey No 14
East
Area Out of Survey No 15
West
Area Out of Survey No 15 oblique 13

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking84 units

0 of 84 units booked (0%), as the promoter reported to MahaRERA

2BHK · 56 units3BHK · 28 units
BuildingTypeCarpet areaUnitsBooked
Wing A2BHK43.08 sq m · 464 sq ft140
Wing A3BHK59.32 sq m · 639 sq ft70
Wing A3BHK60.64 sq m · 653 sq ft70
Wing B2BHK43.08 sq m · 464 sq ft210
Wing B2BHK45.56 sq m · 490 sq ft70
Wing C2BHK43.08 sq m · 464 sq ft140
Wing C3BHK59.32 sq m · 639 sq ft70
Wing C3BHK60.64 sq m · 653 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKapil Laxmikant Thakkar—
Chartered accountantParesh Sabadra—
EngineerJayesh Valjibhai Makwana—
EngineerMuazzam Nazir Shaikh—
EngineerSajid Shaikh—
OtherRasik Patel—
OtherSajid Faiyaz Shaikh—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Wadala Shivar

All 15 projects in Wadala Shivar · Compare Solitaire with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology