7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,204in 103 localities
Registrations4,255some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,255 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date369 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,204 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
P51600030264No date on record——
P51600032657No date on record——
P51600046879No date on record——
P51600048063No date on record——
P51600048117No date on record——
P51600048683No date on record——
P51600049907No date on record——
P51600054675No date on record——
P51600055287No date on record——
P51600076803No date on record——
P51600079545No date on record——
P51600081028No date on record——
Padamalaxmi Row HousesNo date on record——
Palde ResidencyNo date on record——
Panhala ApartmentNaresh Ashokrao BhadakwadeNo date on record——
ParkUttam Ambadas RaiNo date on record——
Park PlazaNo date on record——
Pawan Ganesh Residency SiddhivinayakNo date on record——
Pm1220002500661No date on record——
Pm1220002501095No date on record——
Pm1220002502453No date on record——
Pr1220002501484No date on record——
Pr1220002502707No date on record——
Prabhav Evana Phase - INo date on record——
Pramukh Prasad ApartmentNo date on record——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,255): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology