7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,204in 103 localities
Registrations4,255some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,255 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date369 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,204 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Megh MalharVenus And Dusane DevelopersNo date on record——
Mitanshu AppartmentNo date on record——
Mohanleela ResidencyNo date on record——
Moraya HeightsNo date on record——
morya parashare heightsNo date on record——
Morya ResidencyNo date on record——
morya row houseNo date on record——
Morya V2s4Vasant ConstructionNo date on record——
Mugdha HeightsNo date on record——
Mukund Fakira WaghNo date on record——
Mumbai HouseNo date on record——
Namdeo GalaxyPcg TechnocreteNo date on record——
Nashik Business ParkNo date on record——
Navkar ParadiseNo date on record——
Nirmal Heights 6Gangaprasad Shivprasad SharmaNo date on record——
Nirmal NiwaraNirmal DevelopersNo date on record——
Nishant Iken Phase 2No date on record——
Nityanandadip Co.op. Housing Society Ltd.Dnyaneshwar Pandurang PaldeNo date on record——
Nysa Business CenterNo date on record——
Ocean PearlKashmira Sanjeev RasaneNo date on record——
OlympusOlympus Builders And DevelopersNo date on record——
OMs Premraj EnclaveNo date on record——
Orchid PlazaNo date on record——
P51600004864No date on record——
P51600013133No date on record——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,255): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology